Skip to content
FY2026 GAA: ₱6.79T
PisoScan

HIGH ROCK CONSTRUCTION AND SUPPLIES INCORPORATED (50835) / VILLAR GENERAL CONSTRUCTION AND SUPPLIES

Contractor 695599d700e4c24c6ada

Overview

PhilGEPS awards
₱0 · 0 awards
DPWH contracts
₱669.3M · 7 contracts
Rank by recorded value
#3,382 of 23,487

More info

First record
Dec 31, 2024 (1 yr 10 mo ago)
Latest record
Mar 13, 2025 (1 yr 8 mo ago)
DPWH contractor code
22540

Where they work

Pangasinan₱669.3M
Latest 7 from a total of 7 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
25AI00421 yr 8 mo agoCONSTRUCTION OF RIVER SLOPE/BANK PROTECTION STRUCTURE, SABANGAN RIVER, SAN NICOLAS, PANGASINAN (PACKAGE B)GAA 2025 OO-2On-GoingPangasinan 3rd DEO₱95.3M
25AI00471 yr 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MITURA RIVERS, ASINGAN, PANGASINAN (PACKAGE 1)GAA 2025 OO-2On-GoingPangasinan 3rd DEO₱95.3M
25AI00621 yr 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULANDAYAN RIVER, NATIVIDAD, PANGASINAN (PACKAGE 1)GAA 2025 OO-2On-GoingPangasinan 3rd DEO₱95.2M
25AI00631 yr 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULANDAYAN RIVER, NATIVIDAD, PANGASINAN (PACKAGE 2)GAA 2025 OO-2On-GoingPangasinan 3rd DEO₱95.2M
25AI00641 yr 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULANDAYAN RIVER, SAN NICOLAS, PANGASINAN (PACKAGE 1)GAA 2025 OO-2On-GoingPangasinan 3rd DEO₱95.3M
24AG01871 yr 10 mo agoCONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BANK SLOPE ALONG ALAMINOS RIVER (PALAMIS SECTION) STA. 016+967.6 - STA. 017+351.2, BARANGAY PALAMIS, ALAMINOS CITY, PANGASINANUnprogrammed Appropriations 2024CompletedPangasinan 1st DEO₱96.5M
24AG01881 yr 10 mo agoCONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BANK SLOPE ALONG BALINGCAGUING RIVER (ALOLENG SECTION) STA. 003+296.6 - STA. 003+791.5, BARANGAY ALOLENG, AGNO, PANGASINANUnprogrammed Appropriations 2024CompletedPangasinan 1st DEO₱96.5M

Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.