CLY - ABC BUILDERS
Contractor 8d4e81ea136f9b8712bd
Overview
PhilGEPS awards
₱1.41B · 198 awards
DPWH contracts
₱1.49B · 169 contracts
Rank by recorded value
#1,103 of 23,487
More info
First record
Jan 11, 2010 (16 yrs 10 mo ago)
Latest record
Jul 27, 2026 (3 mos ago)
DPWH contractor code
39231
Where they work
Latest 25 from a total of 169 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 22G00022 | 4 yrs 8 mo ago | ENHANCEMENT OF HOSPITAL, PA HEALTH SERVICE, JAMINDAN, CAPIZGAA 2022 CSSP | Completed | Region VI | ₱48.3M |
| 22GP0015 | 4 yrs 8 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN MIGUEL, DUMALAG, CAPIZBuildings and Facilities | Completed | Capiz 2nd DEO | ₱3.8M |
| 22GP0034 | 4 yrs 8 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BALINGASAG, CUARTERO, CAPIZBuildings and Facilities | Completed | Capiz 2nd DEO | ₱2.0M |
| 21GP0055 | 5 yrs ago | CONCRETING OF BARANGAY ROAD, BRGY. SAN MIGUEL, DUMALAG, CAPIZRoads | Completed | Capiz 2nd DEO | ₱7.6M |
| 21GD0004 | 5 yrs 4 mo ago | RECONSTRUCTION OF CONCRETE PAVEMENT - ILOILO EAST COAST - CAPIZ RD - KO147+000 - KO147+805.5Roads | Completed | Capiz 1st DEO | ₱12.3M |
| 21GP0065 | 5 yrs 4 mo ago | CONCRETING OF MASINALUM, BRGY. SAN ROQUE FMR, BRGY. SAN ROQUE, DUMALAG, CAPIZRoads | Completed | Capiz 2nd DEO | ₱11.9M |
| 21GP0068 | 5 yrs 4 mo ago | CONCRETING OF BRGY. STA. RITA TO BRGY. STO. ROSARIO FMR, BRGY. STA. RITA AND BRGY. STO. ROSARIO, DUMALAG, CAPIZRoads | Completed | Capiz 2nd DEO | ₱12.4M |
| 21GD0024 | 5 yrs 5 mo ago | ROAD WIDENING - MAAYON JCT. BAILAN RD - KO121+274 - KO121+738, KO125+351 - KO127+000Roads | Completed | Capiz 1st DEO | ₱49.0M |
| 21GP0063 | 5 yrs 6 mo ago | OPENING/CONSTRUCTION OF BRGY. STA. RITA TO BRGY. SAN RAFAEL FMR, BRGY. STA. RITA AND BRGY. SAN RAFAEL, DUMALAG, CAPIZRoads | Completed | Capiz 2nd DEO | ₱11.8M |
| 21GP0003 | 5 yrs 8 mo ago | CONCRETING OF BARANGAY ROAD, BARANGAY MIANAY, MUNICIPALITY OF SIGMA, CAPIZRoads | Completed | Capiz 2nd DEO | ₱4.9M |
| 21GP0004 | 5 yrs 8 mo ago | CONCRETING OF BARANGAY ROAD, SITIO NASUNUGAN, BARANGAY MANGOSO, SIGMA, CAPIZRoads | Completed | Capiz 2nd DEO | ₱4.9M |
| 21GP0005 | 5 yrs 8 mo ago | CONCRETING OF BARANGAY ROAD, BARANGAY PARIAN, SIGMA, CAPIZRoads | Completed | Capiz 2nd DEO | ₱4.9M |
| 21GP0013 | 5 yrs 8 mo ago | CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY GANZON, JAMINDAN, CAPIZBuildings and Facilities | Completed | Capiz 2nd DEO | ₱1.9M |
| 21GP0015 | 5 yrs 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAO, CAPIZBuildings and Facilities | Completed | Capiz 2nd DEO | ₱2.5M |
| 21GP0031 | 5 yrs 8 mo ago | ROAD CONCRETING, TAPAZ, CAPIZRoads | Completed | Capiz 2nd DEO | ₱4.9M |
| 21GP0048 | 5 yrs 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE), BARANGAY BALINGASAG, CUARTERO, CAPIZBuildings and Facilities | Completed | Capiz 2nd DEO | ₱1.9M |
| 20GP0076 | 5 yrs 10 mo ago | CONSTRUCTION/REHABILITATION OF FACILITIES FOR PERSON WITH DISABILITIES (PWD) AND ELDERLIES/SENIOR CITIZENS, INCLUDING GENDER-RESPONSIVE FACILITIESBuildings and Facilities | Completed | Capiz 2nd DEO | ₱1.8M |
| 20GD0063 | 5 yrs 11 mo ago | ROAD WIDENING ALONG ILOILO EAST COAST - CAPIZ ROAD KO154+158 - KO155+003Roads | Completed | Capiz 1st DEO | ₱19.6M |
| 20GD0094 | 5 yrs 11 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAAYON, CAPIZBuildings and Facilities | Completed | Capiz 1st DEO | ₱14.8M |
| 20GD0101 | 5 yrs 11 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURES - SITIO SWA, BRGY. POBLACION, PRESIDENT ROXAS, CAPIZFlood Control and Drainage | Completed | Capiz 1st DEO | ₱19.8M |
| 20GD0083 | 6 yrs ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING/COVERED GYM, BRGY. POBLACION, PILAR, CAPIZBuildings and Facilities | Completed | Capiz 1st DEO | ₱4.9M |
| 20GD0090 | 6 yrs ago | CONSTRUCTION OF BRGY. MULTI-PURPOSE BUILDING, BRGY. MADULANO, PRES. ROXAS, CAPIZBuildings and Facilities | Completed | Capiz 1st DEO | ₱3.0M |
| 20GD0099 | 6 yrs ago | CONSTRUCTION OF MULTI-PURPOSE HALL/EVACUATION CENTER AT BRGY. POBLACION ILAYA, MAAYON, CAPIZBuildings and Facilities | Completed | Capiz 1st DEO | ₱4.8M |
| 20GD0105 | 6 yrs ago | COMPLETION/CONSTRUCTION OF BRGY. MULTI-PURPOSE BUILDING/COVERED GYM BRGY. LIBAS, ROXAS CITYBuildings and Facilities | Completed | Capiz 1st DEO | ₱3.0M |
| 20GI0102 | 6 yrs ago | RENOVATION / IMPROVEMENT OF COVERED COURT, BRGY. ZONE 3, SANTA BARBARA, ILOILOBuildings and Facilities | Completed | Iloilo 4th DEO | ₱3.0M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.