PhilGEPS awards
₱0 · 0 awards
DPWH contracts
₱958.1M · 10 contracts
Rank by recorded value
#2,575 of 23,487

More info

First record
Apr 20, 2023 (3 yrs 6 mo ago)
Latest record
Jun 23, 2025 (1 yr 4 mo ago)
DPWH contractor code
50253

Where they work

Latest 10 from a total of 10 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
25OD03461 yr 4 mo agoCONSTRUCTION OF MULTI-PURPOSE FACILITY, (ANCILLARY/ POWERHOUSE FOR LEGISLATIVE BUILDING), BARANGAY KARUHATAN, VALENZUELA CITYBuildings and FacilitiesOn-GoingMetro Manila 3rd DEO₱107.3M
25OD03401 yr 4 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (RESSETLEMENT PROGRAM FOR ISFS), VALENZUELA CITYBuildings and FacilitiesOn-GoingMetro Manila 3rd DEO₱191.2M
25OD03411 yr 4 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MALINTA, VALENZUELA CITYBuildings and FacilitiesOn-GoingMetro Manila 3rd DEO₱95.6M
24DI01172 yrs 1 mo agoCONSTRUCTION OF RIVER PROTECTION STRUCTURE NEAR SOUTH LUZON EXPRESSWAY (SLEX) MALITLIT BRIDGE, STA. ROSA CITY, LAGUNA (PHASE II)GAA 2024 SSPOn-GoingLaguna 2nd DEO₱96.3M
24OD01742 yrs 7 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDNG, PARADA ELEMENTARY SCHOOL, PARADA, VALENZUELA CITYGAA 2024 SSPCompletedMetro Manila 3rd DEO₱60.2M
24OD00782 yrs 8 mo agoCONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG C-3 ROAD (DAGAT-DAGATAN AVENUE - PNR), CALOOCAN CITYFlood Control and DrainageCompletedMetro Manila 3rd DEO₱38.3M
24OD00832 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 10), VALENZUELA CITYGAA 2024 OO-2CompletedMetro Manila 3rd DEO₱94.1M
24OD00842 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 11), VALENZUELA CITYFlood Control and DrainageCompletedMetro Manila 3rd DEO₱94.1M
23OD00903 yrs 6 mo agoCONSTRUCTION OF FLOOD CONTROL WALL ALONG LINGUNAN CREEK, VEINTE REALES, VALENZUELA CITYFlood Control and DrainageCompletedMetro Manila 3rd DEO₱94.3M
23OD00963 yrs 6 mo agoCONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 3), VALENZUELA CITYFlood Control and DrainageCompletedMetro Manila 3rd DEO₱86.8M