DPWH Roads Management Cluster I (Bilateral)

DPWH implementing office dfc60960477d8caab493
Latest 25 from a total of 56 records
Contract IDStartDescriptionStatusContractorAmount
24Z000358 mos agoROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT-AFFECTED AREAS IN MINDANAO, SUB-PROJECT 2 CONTRACT PACKAGE 4, PARANG-BALABAGAN ROAD, STA. 31+320 TO STA. 36+693.67, JICA LOAN AGREEMENT NO. PH-F-P1GAA 2025 FAPsOn-GoingSINO ROAD AND BRIDGE GROUP CO. LTD. (OECO_18941)₱1.69B
24Z000349 mos agoROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT-AFFECTED AREAS IN MINDANAO, SUB-PROJECT 2 CONTRACT PACKAGE 2, PARANG-BALABAGAN ROAD, STA. 8+820 TO STA. 12+780, JICA LOAN AGREEMENT NO. PH-F-P1GAA 2025 FAPsOn-GoingCHINA WUYI CO., LTD (OECO_16634)₱1.50B
24Z000369 mos agoAWP 3/PREVENTIVE MAINTENANCE-ASPHALT OVERLAY-SAN MIGUEL SECTION-DAANG MAHARLIKA HIGHWAY, PROVINCE OF BULACANGAA 2024 FAPsOn-Going729 CONSTRUCTION, INC. (FORMERLY 722 CONSTRUCTION, INC.)₱95.5M
24Z000291 yr agoSUB-PROJECT 9 CONTRACT PACKAGE 2, MANUANGAN-PARANG ROAD, CP-2: STA. 7+680 - STA. 10+480GAA 2025 FAPsOn-GoingCHINA WUYI CO., LTD (OECO_16634)₱1.61B
24Z000281 yr 1 mo agoROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT-AFFECTED AREAS IN MINDANAO (RNDP - CAAM) SUB-PROJECT 9 CONTRACT PACKAGE 1, MANUANGAN-PARANG ROAD, CP-1A: STA. 0+000 - STA. 7+680, CP-1B: STA. 10+480 - STA. 17+418.82, JICA LOAN AGREEMENT NO. PH-F-P1GAA 2025 FAPsOn-GoingSINO ROAD AND BRIDGE GROUP CO. LTD. (OECO_18941)₱1.67B
24Z000321 yr 4 mo agoAWP 3/PREVENTIVE MAINTENANCE-PULILAN-BALIUAG BY-PASS ROAD, BALIUAG, BULACAN, PROVINCE OF BULACANGAA 2024 FAPsOn-GoingL.R. TIQUI BUILDERS, INC.₱95.1M
24Z000311 yr 4 mo agoAWP 3/PREVENTIVE MAINTENANCE-REPAIR/REHABILITATION/IMPROVEMENT OF CONCRETE SLOPE PROTECTION ALONG PLARIDEL BYPASS ROAD, GUIGUINTO, PLARIDEL AND BUSTOS, BULACAN, PROVINCE OF BULACANGAA 2024 FAPsOn-GoingC.E.M. CONSTRUCTION, INC.₱48.8M
24Z000091 yr 5 mo agoSUB-PROJECT 8, PARANG EAST DIVERSION ROAD, STA. 0+000 - STA. 7+074.29GAA 2024 FAPsOn-GoingCHINA GEO-ENGINEERING CORPORATION (OECO_3427) / R.D. INTERIOR JUNIOR CONSTRUCTION₱1.38B
24K004881 yr 10 mo agoPREVENTIVE MAINTENANCE-PRIMARY ROADS, SAYRE HIGHWAY K1475+006-K1475+426, K1475+455-K1476+027, K1479+000-K1480+000, K1480+1882-K1482+205, K1502+000-K1503+000,K1518+(-182)-K1518+000,K1519+283-K1520+000,K1522+000-K1522+568, K1525+109-K1525+207GAA 2024 FAPsCompletedM. MONTESCLAROS ENTERPRISES, INC.₱289.5M
21Z000071 yr 11 mo agoDAVAO CITY BYPASS CONSTRUCTION PROJECT (DCBCP) PACKAGE I-2, STA. 0+000 TO STA. 12+800, FUNDED UNDER JICA LOAN AGREEMENT NO. PH-273GAA 2023 FAPsOn-GoingSHIMIZU CORPORATION (OECO_16693) / TAKENAKA CIVIL ENGINEERING & CONSTRUCTION CO., LTD. (OECO_29591) / ULTICON BUILDERS, INC.₱9.11B
24N001961 yr 11 mo agoBUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY ROAD (AGUSAN-MISAMIS OR ROAD)- K1253+544.32- K1256+165, K1256+322- K1259+812, K1263+828- K1264+956, AGUSAN DEL NORTEGAA 2024 FAPsCompletedTRIPARCO DEVELOPMENT CORPORATION₱299.0M
24Z000022 yrs 3 mo agoPROPOSED SITE DEVELOPMENT FOR PROJECT MANAGEMENT OFFICE IN BALO-I, LANAO DEL NORTEMulti Purpose Buildings, RoadsOn-GoingA.M. DYNAMIC CONSTRUCTION₱28.2M
21Z000082 yrs 10 mo agoDAVAO CITY BYPASS CONSTRUCTION PROJECT (II), PACKAGE I-3 STA. 23+500 - STA. 29+700GAA 2022 FAPsOn-GoingSHIMIZU CORPORATION (OECO_16693) / TAKENAKA CIVIL ENGINEERING & CONSTRUCTION CO., LTD. (OECO_29591) / ULTICON BUILDERS, INC.₱9.71B
23CC04472 yrs 11 mo agoPREVENTIVE MAINTENANCE OF REPAIR/REHAB./IMP. OF CONCRETE SLOPE PROTECTION ALONG PLARIDEL BY-PASS ROAD, BUSTOS, BUILACAN, PM COMPONENT OF THE ROAD UPGRADING AND PRESERVATION PROJECT (RUPP) UNDER JAPAN INTERNATIONAL COOPERATION AGENCY (JICA), BUSTOS, BULACARoadsCompletedC.E.M. CONSTRUCTION, INC.₱28.9M
22Z000273 yrs 3 mo agoDAVAO CITY BYPASS CONSTRUCTION PROJECT, PACKAGE II (NORTH SECTION), CONTRACT PACKAGE II-2 (STA. 32+240 TO STA. 35+760)GAA 2022 FAPsOn-GoingAIMM BUILDER AND CONSTRUCTION SUPPLY (35678) / CHINA ROAD & BRIDGE CORPORATION (OECO_3319) / NATIONSTAR DEVELOPMENT CORPORATION (FOR: CASMOR CONSTRUCTION CORPORATION)₱4.96B
21Z000223 yrs 9 mo agoDAVAO CITY BYPASS CONSTRUCTION PROJECT PACKAGE II (NORTH SECTION) CONTRACT PACKAGE II-1 (STA. 29+700 TO STA. 32+240), DAVAO CITYGAA 2022 FAPsOn-GoingCAVDEAL-CAVITE IDEAL INT'L. CONST. & DEV'T. CORP. (5599) / COASTLAND CONSTRUCTION & DEVELOPMENT CORP. (11487) / WEE ENG CONSTRUCTION, INC.₱4.33B
22Z000114 yrs 3 mo agoAWP3/PREVENTIVE MAINTENANCE, REPLACEMENT OF ILOG BAKOD BRIDGE (BO16825LZ) ALONG DAANG MAHARLIKA, SAN MIGUEL, BULACAN, PM COMPONENT OF THE ROAD UPGRADING & PRESERVATION PROJ. (RUPP) UNDER JAPAN INT'L. COOPERATIVE AGENCY (JICA), LOAN AGREEMENT NO. PH-P247,BridgesCompletedL.R. TIQUI BUILDERS, INC.₱28.4M
21C001084 yrs 10 mo agoREPAIR/REHABILITATION OF PLARIDEL BYPASS UNDER THE ANNUAL WORK PROGRAM 3, ASSET PRESERVATION CONTRACT (APC) COMPONENT, ROAD UPGRADING AND PRESERVATION PROJECT, JICA LOAN AGREEMENT NO. PH-P247, PROVINCE OF BULACANRoadsCompletedL.R. TIQUI BUILDERS, INC. (13810) / R.A. PAHATI CONST. & SUPPLY, INC.₱115.8M
21K002154 yrs 11 mo agoANNUAL WORK PROGRAM 3/PREVENTIVE MAINTENANCE OF SAYRE HIGHWAY, K1468+031 - K1468+882, K1470+000 - K1470+125, K1470+920 - K1471+000, K1473+539 - K1474+1013, PROVINCE OF BUKIDNON UNDER THE ROAD UPGRADING AND PRESERVATION PROJECT, ASSET PRESERVATION CONTRACTRoadsCompletedM. MONTESCLAROS ENTERPRISES, INC.₱193.0M
21C000895 yrs 1 mo agoREHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, UNDER THE ANNUAL WORK PROGRAM 3, ASSET PRESERVATION CONTRACT (APC) COMPONENT, ROAD UPGRADING AND PRESERVATION PROJECT, PROVINCE OF BULACANRoadsCompletedIM CONSTRUCTION CORPORATION₱154.3M
21CC02805 yrs 2 mo agoIMPLEMENTATION OF CIVIL WORKS FOR THE CONCRETE SLOPE PROTECTION OF PLARIDEL BYPASS ACCESS ROAD NO. 2 UNDER THE ANNUAL WORK PROGRAM 3 ASSET PRESERVATION CONTRACT (APC) COMPONENT, ROAD UPGRADING AND PRESERVATION PROJECT, JICA LOAN AGREEMENT NO PH-P247, PLARRoadsCompletedC.E.M. CONSTRUCTION, INC. (36501) / D.R. ROBLES CONSTRUCTION₱46.3M
20Z000115 yrs 5 mo agoMARAWI TRANSCENTRAL ROAD, PHASE III, UNDER ROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT AFFECTED AREAS IN MINDANAO (RNDP-CAAM), JICA LOAN AGREEMENT NO. PH-F-P1, CONTRACT PACKAGE 3-C, REHABILITATION OF TRANSCENTRAL ROADS, MARAWI CITY, LANAO DEL SURRoadsCompletedAL HUSSEIN CONSTRUCTION₱157.8M
20Z000095 yrs 6 mo agoMARAWI TRANSCENTRAL ROAD, PHASE III, UNDER ROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT AFFECTED AREAS IN MINDANAO (RNDP-CAAM), JICA LOAN AGREEMENT NO. PH-F-P1, CONTRACT PACKAGE 3-A, REHABILITATION OF TRANSCENTRAL ROADS, MARAWI CITY, LANAO DEL SURGAA 2021 FAPsOn-GoingFIAT CONSTRUCTION SERVICES (05463) / M.M.A. ACHIEVER CONSTRUCTION & DEVELOPMENT CORP.₱215.4M
20Z000105 yrs 6 mo agoMARAWI TRANSCENTRAL ROAD, PHASE III, UNDER ROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT AFFECTED AREAS IN MINDANAO (RNDP-CAAM), JICA LOAN AGREEMENT NO. PH-F-P1, CONTRACT PACKAGE 3-B, REHABILITATION OF TRANSCENTRAL ROADS, MARAWI CITY, LANAO DEL SURRoadsOn-GoingKOUZBARY BUILDERS (36446) / RENREN TRADING AND CONSTRUCTION SERVICES₱173.4M
20Z000125 yrs 6 mo agoMARAWI TRANSCENTRAL ROAD, PHASE III, UNDER ROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT AFFECTED AREAS IN MINDANAO (RNDP-CAAM), JICA LOAN AGREEMENT NO. PH-F-P1, CONTRACT PACKAGE 3-D, REHABILITATION OF TRANSCENTRAL ROADS, MARAWI CITY, LANAO DEL SURRoadsCompletedCDH CONSTRUCTION₱173.2M