Skip to content
FY2026 GAA: ₱6.79T
PisoScan

ALPIZ CONSTRUCTION AND DEVELOPMENT CORPORATION

Contractor 396922892fb7c3539b81

Overview

PhilGEPS awards
₱1.10B · 51 awards
DPWH contracts
₱838.1M · 30 contracts
Rank by recorded value
#1,497 of 23,487

More info

First record
May 31, 2011 (15 yrs 5 mo ago)
Latest record
Aug 27, 2025 (1 yr 2 mo ago)
DPWH contractor code
11039

Where they work

Latest 25 from a total of 30 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
25CI00101 yr 8 mo agoSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALASAS CREEK (PHASE I), BARANGAY SAN AGUSTIN, MAGALANG, PAMPANGAFlood Control and DrainageCompletedPampanga 3rd DEO₱49.0M
25CI00111 yr 8 mo agoSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALASAS CREEK (PHASE II), BARANGAY SAN AGUSTIN, MAGALANG, PAMPANGAFlood Control and DrainageCompletedPampanga 3rd DEO₱49.0M
24CK00432 yrs 8 mo agoREHABILITATION OF EXISTING DIKE ALONG O'DONNELL RIVER (BUENO SECTION, LEFT BANK), PHASE 7, CAPAS, TARLACFlood Control and DrainageCompletedTarlac 2nd DEO₱96.5M
24CI00022 yrs 9 mo agoFLOOD MANAGEMENT PROGRAM:CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF REINFORCED CONCRETE SLOPE PROTECTION ALONG QUITANGIL RIVER, BARANGAY SAN AGUSTIN, MAGALANG, PAMPANGAFlood Control and DrainageCompletedPampanga 3rd DEO₱49.0M
23CI01113 yrs 6 mo agoSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DIKE WITH SLOPE PROTECTION AND GROUNDSILL ALONG QUITANGIL CREEK (RIGHTSIDE), BRGYS SAN MIGUEL-TUFlood Control and DrainageCompletedPampanga 3rd DEO₱72.3M
23OF00853 yrs 7 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING, (DISASTER RESPONSE CENTER) AT BRGY. PASONG TAMO, QUEZON CITYBuildings and FacilitiesCompletedQuezon City 1st DEO₱28.8M
22OF01034 yrs 5 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE AND TRIBUTARIES, BARANGAY BAGONG SILANGAN, QUEZON CITYFlood Control and DrainageCompletedQuezon City 1st DEO₱18.8M
21OF00185 yrs 8 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURES AND TRIBUTARIES, BRGY. PAYATAS (PHASE 7), QUEZON CITYFlood Control and DrainageCompletedQuezon City 1st DEO₱48.0M
20OF01795 yrs 11 mo agoCONSTRUCTION OF TANGALI ST. AND TINAGAN SR., BRGY. SAN JOSE, QUEZON CITYRoadsCompletedQuezon City 1st DEO₱28.5M
20OF02556 yrs 1 mo agoCONSTRUCTION/ REHABILITATION OF MLO PTA OFFICE, BRGY. COMMONWEALTH, QUEZON CITYBuildings and FacilitiesCompletedQuezon City 1st DEO₱2.9M
20OF02586 yrs 1 mo agoCONSTRUCTION/ REHABILITATION OF MARKET AT BAGONG SILANGAN EXTENSION IN FRONT OF MARKET(TERMINAL(, QUEZON CITYBuildings and FacilitiesCompletedQuezon City 1st DEO₱2.9M
20OF00096 yrs 4 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURES AND TRIBUTARIES, BRGY. PAYATAS (PHASE 6), QUEZON CITYFlood Control and DrainageCompletedQuezon City 1st DEO₱47.8M
19OF00337 yrs 4 mo agoCONSTRUCTION OF FLOOD CONTROL STRUCTURE BRGY. PAYATAS (PHASE 5), Q.C.Flood Control and DrainageCompletedQuezon City 1st DEO₱46.5M
19OF00977 yrs 5 mo agoREHABILITATION OF PAVED ROAD - IMPROVEMENT OF BIAK NA BATO STREET, Q.C.RoadsCompletedQuezon City 1st DEO₱33.3M
19OF01257 yrs 5 mo agoREHABILITATION OF SAN ANTONIO STREET, Q.C.RoadsCompletedQuezon City 1st DEO₱28.3M
18OF00078 yrs 8 mo agoROAD/IMPROVEMENT OF SPEAKER PEREZ ST., (PHASE II), Q.C.RoadsCompletedQuezon City 1st DEO₱18.5M
18OF00178 yrs 8 mo agoREHABILITATION/IMPROVEMENT OF DRAINAGE SYSTEM OF SPEAKER PEREZ (PHASE II), Q.C.Flood Control and DrainageCompletedQuezon City 1st DEO₱9.2M
18OF00468 yrs 8 mo agoREHABILITATION IMPROVEMENT OF DRAINAGE SYSTEM OF APO ST., Q.C.Flood Control and DrainageCompletedQuezon City 1st DEO₱27.9M
18OF00768 yrs 8 mo agoCONCRETING OF ROAD 20, BRGY. BAHAY TORO, Q.C.RoadsCompletedQuezon City 1st DEO₱3.9M
17OF01379 yrs 1 mo agoREHABILITATION/ IMPROVEMENT OF BALON BATO CREEK AND TRIBUTARIES, BRGY. BALON BATO, QUEZON CITYFlood Control and DrainageCompletedQuezon City 1st DEO₱18.4M
17OF00859 yrs 3 mo agoIMPROVEMENT/REHABILITATION OF ROAD 20, BRGY. BAHAY TORO (PHASE III) , QUEZON CITYRoadsCompletedQuezon City 1st DEO₱14.0M
17OF00299 yrs 7 mo agoCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE OF CALAMBA STREET, Q.C.Flood Control and DrainageCompletedQuezon City 1st DEO₱9.1M
16OF01349 yrs 8 mo agoREHABILITATION AND IMPROVEMENT OF SPEAKER PERES ST., QUEZON CITYFlood Control/Hydraulics/Drainage, Roads: Rehabilitation - PCCPCompletedQuezon City 1st DEO₱18.3M
16OF01409 yrs 8 mo agoREHABILITATION OF FLOOD CONTROL STRUCTURES ANF TRIBUTARIES AT BRGY. PAYATAS, QUEZON CITYFlood Control and DrainageCompletedQuezon City 1st DEO₱27.5M
16OF001210 yrs 7 mo agoREHABILITATION OF FLOOD CONTROL STRUCTURES & TRIBUTARIES BRGY. PAYATAS, Q.C.Flood Control and DrainageCompletedQuezon City 1st DEO₱22.2M

Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.