E E CONSTRUCTION
Contractor 57161390edae89df81af
Overview
PhilGEPS awards
₱0 · 0 awards
DPWH contracts
₱532.7M · 39 contracts
Rank by recorded value
#3,941 of 23,487
More info
First record
Jul 14, 2019 (7 yrs 4 mo ago)
Latest record
May 21, 2025 (1 yr 5 mo ago)
DPWH contractor code
45017
Where they work
Oriental Mindoro₱532.7M
Latest 25 from a total of 39 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 25ED0176 | 1 yr 5 mo ago | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN CARLOS, NAUJAN, ORIENTAL MINDOROGAA 2025 SSP | Completed | Mindoro Oriental DEO | ₱4.9M |
| 25EI0104 | 1 yr 7 mo ago | CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY BONBON, MANSALAY, ORIENTAL MINDORO, PHASE IIGAA 2025 SSP | Completed | Southern Mindoro DEO | ₱2.9M |
| 25EI0021 | 1 yr 8 mo ago | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF PROTECTION WORKS AND DRAINAGE SYSTEM, BANSUD RIS, BANSUD, ORIENTAL MINDOROGAA 2025 OO-2 | On-Going | Southern Mindoro DEO | ₱14.7M |
| 24ED0121 | 2 yrs 5 mo ago | CONSTRUCTION OF ROAD, BRGY. COMUNAL, CALAPAN CITY, ORIENTAL MINDOROGAA 2024 SSP | Completed | Mindoro Oriental DEO | ₱4.8M |
| 24EI0118 | 2 yrs 6 mo ago | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BALATASAN NATIONAL HIGH SCHOOL, BARANGAY BALATASAN, BULALACAO, ORIENTAL MINDOROGAA 2024 DepEd BEFF | Completed | Southern Mindoro DEO | ₱6.0M |
| 24ED0056 | 2 yrs 9 mo ago | CONSTRUCTION OF RIVER CONTROL ALONG SITIO BAGONG POOK, BARANGAY GUTAD, CALAPAN CITY, ORIENTAL MINDOROGAA 2024 OO-2 | Completed | Mindoro Oriental DEO | ₱49.0M |
| 24EI0025 | 2 yrs 9 mo ago | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) SAN ROQUE - SAN JUAN - TAFARMA ROAD, BRGY. SAN JUAN, BULALACAO, ORIENTAL MINDOROGAA 2024 CP | Completed | Southern Mindoro DEO | ₱9.8M |
| 24EI0029 | 2 yrs 9 mo ago | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - BRGY. MALUBAY TO BRGY. BUONG LUPA TO WALANG LANGIT FALLS, GLORIA, ORIENTAL MINDOROGAA 2024 CP | Completed | Southern Mindoro DEO | ₱14.7M |
| 23EI0114 | 3 yrs ago | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MALIWANAG, MANSALAY, ORIENTAL MINDOROUnprogrammed Appropriations 2023 | Completed | Southern Mindoro DEO | ₱2.9M |
| 23EI0091 | 3 yrs 3 mo ago | CONSTRUCTION OF 1 STY 3 CL SCHOOL BUILDING AT FORMON NHS, BONGABONG, ORIENTAL MINDOROGAA 2023 DepEd BEFF | Completed | Southern Mindoro DEO | ₱9.0M |
| 23ED0010 | 3 yrs 7 mo ago | CONSTRUCTION OF ROAD, SITIO ILAYA, MANAGPI, CALAPAN, ORIENTAL MINDOROGAA 2023 CSSP | Completed | Mindoro Oriental DEO | ₱9.8M |
| 23EI0035 | 3 yrs 7 mo ago | CONSTRUCTION OF ROAD AT BARANGAY MALO, BANSUD, ORIENTAL MINDOROGAA 2023 CSSP | Completed | Southern Mindoro DEO | ₱4.9M |
| 23ED0034 | 3 yrs 8 mo ago | CONSTRUCTION OF MAIDLANG RIVER CONTROL, CALAPAN CITY, ORIENTAL MINDOROGAA 2023 OO-2 | Completed | Mindoro Oriental DEO | ₱33.8M |
| 21EI0158 | 4 yrs 7 mo ago | CONCRETING OF BULALACAO DIVERSION ROAD PHASE II, CAMPAASAN SECTION, BULALACAO, ORIENTAL MINDOROGAA 2021 LP | Completed | Southern Mindoro DEO | ₱29.4M |
| 21EI0167 | 4 yrs 7 mo ago | CONCRETING OF ROAD, SITIO LAWAY, BRGY. SALCEDO - SITIO ILAYA - BRGY. TIGUISAN, BANSUD, ORIENTAL MINDOROGAA 2021 LP | Completed | Southern Mindoro DEO | ₱19.6M |
| 22ED0035 | 4 yrs 8 mo ago | REHABILITATION (COMPLETION) OF EVACUATION CENTER (REHABILITATION AND RECOVERY PLAN (RBP) FOR COVID-19), BRGY. ZONE I, SOCORRO, ORIENTAL MINDOROGAA 2022 LP | Completed | Mindoro Oriental DEO | ₱2.0M |
| 22ED0015 | 4 yrs 8 mo ago | CONSTRUCTION OF MAYABIG RIVER CONTROL (SITIO BALIKAT), BACO, ORIENTAL MINDOROGAA 2022 CSSP | Completed | Mindoro Oriental DEO | ₱4.8M |
| 22ED0009 | 4 yrs 8 mo ago | CONSTRUCTION OF ROAD, BARANGAY MONTEVERDE, SOCORRO, ORIENTAL MINDOROGAA 2022 CSSP | Completed | Mindoro Oriental DEO | ₱4.8M |
| 22EI0007 | 4 yrs 8 mo ago | WIDENING OF PERMANENT BRIDGES: PINAG - AGAWAN BR. (B00216MR) ALONG CALAPAN SOUTH ROAD, BANSUD, ORIENTAL MINDOROGAA 2022 OO-1 | Completed | Southern Mindoro DEO | ₱15.5M |
| 22EI0019 | 4 yrs 8 mo ago | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - INTERNAL ACCESS ROAD TO SITIO PALAMANG, MANIHALA LEADING TO MANIHALA WATERFALLS II, BANSUD, ORIENTAL MINDOROGAA 2022 CSSP | Completed | Southern Mindoro DEO | ₱14.7M |
| 22EI0041 | 4 yrs 8 mo ago | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF BONGABONG RIVER CONTROL, BARANGAY SAN JOSE SECTION, BONGABONG, ORIENTAL MINDOROGAA 2022 CSSP | Completed | Southern Mindoro DEO | ₱17.3M |
| 21EI0093 | 5 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN FRANCISCO, BULALACAO, ORIENTAL MINDOROGAA 2021 LP | Completed | Southern Mindoro DEO | ₱4.0M |
| 21EI0121 | 5 yrs 7 mo ago | CONCRETING OF BRGY. ANILAO ROAD, BONGABONG, ORIENTAL MINDOROGAA 2021 LP | Completed | Southern Mindoro DEO | ₱10.4M |
| 21EI0017 | 5 yrs 8 mo ago | CONSTRUCTION/REHABILITATION OF FLOOD CONTROL MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF SUMAGUI RIVER CONTROL (UPSTREAM), MANIHALA-VILLA PAG-ASA SECTION, BANSUD, ORIENTAL MINDOROGAA 2021 OO-2 | Completed | Southern Mindoro DEO | ₱29.4M |
| 21EI0027 | 5 yrs 8 mo ago | CONSTRUCTION OF BONGABONG RIVER CONTROL, BARANGAY SAN JOSE SECTION, BONGABONG, ORIENTAL MINDOROGAA 2021 OO-2 | Completed | Southern Mindoro DEO | ₱24.5M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.