Project 22ED0035

DPWH infrastructure contract
Contract ID:
22ED0035
Fingerprint:
c3adf501807531…322d70d5bf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2022 (4 yrs 8 mo ago) · Target/actual end May 27, 2022
Description:
REHABILITATION (COMPLETION) OF EVACUATION CENTER (REHABILITATION AND RECOVERY PLAN (RBP) FOR COVID-19), BRGY. ZONE I, SOCORRO, ORIENTAL MINDORO
Category:
GAA 2022 LP
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
E E CONSTRUCTION · DPWH contractor code 45017
Contract amount:
₱1,959,777.03 (₱2.0M)
Funding source:
Regular Infra - GAA 2022 LP
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ED0105May 26, 2025PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0046+000 - K0047+462, ORIENTAL MINDOROCompleted₱115.8M
25ED0106May 26, 2025PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0049+000 - K0050+765, ORIENTAL MINDOROCompleted₱82.0M
25ED0108May 26, 2025INSTALLATION OF STREET LIGHTS ALONG CALAPAN SOUTH ROAD K0047+200 - K0060+800, SOCORRO, ORIENTAL MINDOROCompleted₱95.1M
25ED0123May 26, 2025PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0062+000 - K0063+015, ORIENTAL MINDOROCompleted₱106.1M
25ED0125May 26, 2025PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0050+765 - K0052+246, ORIENTAL MINDOROCompleted₱86.8M
25ED0126May 26, 2025PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0052+246 - K0053+511, ORIENTAL MINDOROOn-Going₱57.9M
25ED0127May 26, 2025PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0061+129 - K0062+000, ORIENTAL MINDOROCompleted₱72.4M
25ED0134May 26, 2025REHABILITATION OF BRGY. LEUTEBORO I - BRGY. MATUNGAO ROAD, SOCORRO, ORIENTAL MINDOROCompleted₱144.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.