PhilGEPS awards
₱1.95B · 489 awards
DPWH contracts
₱479.4M · 75 contracts
Rank by recorded value
#1,250 of 23,487
More info
First record
Sep 5, 2012 (14 yrs 2 mo ago)
Latest record
Sep 23, 2026 (1 mo ago)
DPWH contractor code
20795
Where they work
Latest 25 from a total of 75 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 26MI0052 | 1 mo ago | R1 - CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY NEW KALIBO, MLANG, COTABATO, 6.930094, 124.943695GAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱4.9M |
| 26MI0058 | 2 mos ago | R1 - CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BRGY. TAWANTAWAN, MLANG, COTABATO, 6.932822, 124.914543GAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱4.9M |
| 26MI0087 | 2 mos ago | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. LA FORTUNA, MLANG, COTABATO, 6.870884, 124.95327GAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱4.9M |
| 26MI0112 | 2 mos ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (POLICE AND FIRE SUB-STATION) IN BRGY. BANAYAL, TULUNAN, COTABATO, 6.848724, 124.981747GAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱9.9M |
| 26MI0008 | 4 mos ago | (RE-BID) - CONSTRUCTION OF ROAD, STA. 0+000 - STA. 0 + 250, BARANGAY BATANG, TULUNAN, COTABATOGAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱4.7M |
| 26MI0015 | 4 mos ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY NEW CARIDAD, TULUNAN, COTABATO, 6.87639, 125.013997GAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱4.9M |
| 26MI0053 | 4 mos ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. LIBOO, MLANG, COTABATO, 6.963859, 124.93495GAA 2026 SSP | On-Going | Cotabato 3rd DEO | ₱4.8M |
| 25MI0113 | 8 mos ago | REPAIR/REHABILITATION OF CLASSROOMS, LIKA NATIONAL HIGH SCHOOL, MLANG, NORTH COTABATOGAA 2025 DEPED BEFF | Completed | Cotabato 3rd DEO | ₱7.9M |
| 25MI0111 | 8 mos ago | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MANUBUAN, MATALAM, NORTH COTABATOGAA 2025 SSP | Completed | Cotabato 3rd DEO | ₱4.9M |
| 25MI0091 | 1 yr 2 mo ago | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. NEW ANTIQUE, MLANG, COTABATOGAA 2025 SSP | On-Going | Cotabato 3rd DEO | ₱4.7M |
| 25MI0068 | 1 yr 3 mo ago | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. NEW RIZAL, MLANG, COTABATOGAA 2025 SSP | Completed | Cotabato 3rd DEO | ₱4.7M |
| 25MI0077 | 1 yr 3 mo ago | CONSTRUCTION OF ROAD FROM PUROK 4 TO PUROK 6 IN BRGY. MAGBOK, TULUNAN, COTABATOGAA 2025 SSP | Completed | Cotabato 3rd DEO | ₱4.7M |
| 25MI0084 | 1 yr 3 mo ago | CONSTRUCTION OF ROAD FROM PUROK 4 TO PUROK 6 IN BRGY. LANGKONG, MLANG, COTABATOGAA 2025 SSP | Completed | Cotabato 3rd DEO | ₱9.4M |
| 25MI0014 | 1 yr 5 mo ago | MAKILALA-ALLAH VALLEY RD - K1621 + 000 - K1621 + 040GAA 2025 OO-1 | Completed | Cotabato 3rd DEO | ₱6.9M |
| 25MI0018 | 1 yr 5 mo ago | CONSTRUCTION OF KABACAN RIS, DRAINAGE RESHAPING AT MAYASONG - HINIGARAN, KABACAN, COTABATOGAA 2025 OO-2 | Completed | Cotabato 3rd DEO | ₱9.8M |
| 25MI0020 | 1 yr 5 mo ago | CONSTRUCTION OF KABACAN RIS, DRAINAGE RESHAPING AT PALYA, KABACAN, COTABATOFlood Control and Drainage | Completed | Cotabato 3rd DEO | ₱9.8M |
| 25MI0059 | 1 yr 7 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TAWAN-TAWAN, MLANG, NORTH COTABATOBuildings and Facilities | Completed | Cotabato 3rd DEO | ₱4.7M |
| 25MI0060 | 1 yr 7 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY NEW RIZAL, MLANG, NORTH COTABATOBuildings and Facilities | Completed | Cotabato 3rd DEO | ₱9.4M |
| 25MI0007 | 1 yr 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DIGITAL LEARNING CENTER), BARANGAY POBLACION, TULUNAN, NORTH COTABATOGAA 2025 SSP | Completed | Cotabato 3rd DEO | ₱4.9M |
| 25MI0037 | 1 yr 8 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY SIBSIB, TULUNAN, NORTH COTABATOBuildings and Facilities | Completed | Cotabato 3rd DEO | ₱4.9M |
| 25MI0040 | 1 yr 8 mo ago | BUAYAN-LEPAGA-GAUNAN ROAD IN SUPPORT TO CAVENDISH BANANA PROJECT, MLANG, COTABATOGAA 2025 CP | Completed | Cotabato 3rd DEO | ₱39.2M |
| 24MI0105 | 1 yr 8 mo ago | CONSTRUCTION OF PALMA PEREZ-LA SUERTE ROAD FROM BARANGAY PALMA PEREZ TO BARANGAY LA SUERTE, MLANG, COTABATOUnprogrammed Appropriations 2024 | On-Going | Cotabato 3rd DEO | ₱14.4M |
| 24MI0108 | 1 yr 8 mo ago | CONSTRUCTION OF ROAD IN BARANGAY BUNAWAN, TULUNAN, COTABATOUnprogrammed Appropriations 2024 | On-Going | Cotabato 3rd DEO | ₱14.4M |
| 24M00097 | 2 yrs ago | CONSTRUCTION OF DRAINAGE CANAL, STA. 0+000 - STA. 0+072.095, BARANGAY ARINGAY, KABACAN, COTABATOFlood Control and Drainage | Completed | Region XII | ₱9.9M |
| 24MI0094 | 2 yrs ago | CONSTRUCTION (COMPLETION) OF THE BUILDING OF THE 3RD DISTRICT ENGINEERING OFFICE, PROVINCE OF COTABATO (PHASE 2)Buildings and Facilities | Completed | Cotabato 3rd DEO | ₱9.9M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.