Skip to content
FY2026 GAA: ₱6.79T
PisoScan

HKBT CONSTRUCTION

Contractor b5cb526475f6db6da6d2

Overview

PhilGEPS awards
₱181.6M · 35 awards
DPWH contracts
₱187.9M · 15 contracts
Rank by recorded value
#4,974 of 23,487

More info

First record
Mar 11, 2021 (5 yrs 8 mo ago)
Latest record
Jun 26, 2026 (4 mos ago)
DPWH contractor code
48936

Where they work

Kalinga₱369.5M
Latest 15 from a total of 15 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
26PK00034 mos agoORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS- MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CAGALUAGAA 2026 OO-1On-GoingUpper Kalinga DEO₱21.1M
25PL00351 yr 7 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY NEW TANGLAG (B/S),GAA 2025 OO-2On-GoingLower Kalinga DEO₱28.9M
25PL00361 yr 7 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALOFlood Control and DrainageOn-GoingLower Kalinga DEO₱19.3M
25PL00491 yr 7 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANANIG RIVER AT CULLAYAFlood Control and DrainageOn-GoingLower Kalinga DEO₱4.9M
25PK00241 yr 7 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONGFlood Control and DrainageCompletedUpper Kalinga DEO₱4.9M
24PK00532 yrs 6 mo agoORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES - TERTIARY ROADS ALONG LUBUAGAN - BATONG BUHAY - ABRA BOUNDARY ROAD, LUBUAGAN, KGAA 2024 OO-1On-GoingUpper Kalinga DEO₱8.7M
24PK00302 yrs 6 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL ALONG CHICO RIVFlood Control and DrainageCompletedUpper Kalinga DEO₱29.4M
23PK00773 yrs 4 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL ALONG CHICO RIVFlood Control and DrainageCompletedUpper Kalinga DEO₱4.9M
23PK00343 yrs 8 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL AT KABIGGEN, STA. 180+690 - STA.180+850 (RS)Flood Control and DrainageCompletedUpper Kalinga DEO₱9.8M
23PK00063 yrs 8 mo agoORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL (LIGLIG GIIPO)Flood Control and DrainageCompletedUpper Kalinga DEO₱16.6M
22PK00314 yrs 7 mo agoORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: TERTIARY ROADS ALONG LUBUAGAN - BATONG BUHAY - ABRA BOUNDARY ROAD, LUBUAGAN, KARoadsCompletedUpper Kalinga DEO₱1.7M
22PK00664 yrs 7 mo agoCONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR SYSTEM - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SYSTEM, BARANGAY COMMUNITY WATERWORKS IN OLATA, BARANGAY MABILONGWater Provision and StorageCompletedUpper Kalinga DEO₱14.7M
21PL00854 yrs 7 mo agoCONSTRUCTION (COMPLETION) OF ISLA/MALLONG, /DUENAK/LAY-ASAN/EMPLOYEES VILLAGE FOOTBRIDGE W/ SLOPE PROTECTION, TABUK CITY/TANUDAN, KALINGABridgesTerminatedLower Kalinga DEO₱1.6M
21P001165 yrs ago(1) RECONSTRUCTION OF THE BAMBOO FOOTBRIDGE AT SAMANG CREEK, SAKKI-ING FOOTBRIDGE AND KALIMANGOWAN FOOTBRIDGE, SITIO PAYAO, BRGY. LOWER UMA, LUBUAGAN, KALINGA(2) RECONSTRUCTION OF SUKLAP SUSPENSION FOOTBRIDGE, SUKLAP, BRGY. TANGLAG, LUBUAGAN KALINGA(3BridgesCompletedCordillera Administrative Region₱19.3M
21PL00695 yrs 7 mo agoIMPROVEMENT OF RIVERSIDE/SITIO SUMADEL DRAINAGE CANAL SYSTEM, TABUK CITY, KALINGAFlood Control and DrainageCompletedLower Kalinga DEO₱2.0M

Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.