Skip to content
FY2026 GAA: ₱6.79T
PisoScan

ED1SON DEVELOPMENT & CONSTRUCTION INC.

Contractor c1bc4a475858dc0d785c

Overview

PhilGEPS awards
₱19.72B · 235 awards
DPWH contracts
₱8.99B · 359 contracts
Rank by recorded value
#83 of 23,487

More info

First record
Jan 21, 2016 (10 yrs 9 mo ago)
Latest record
Jul 17, 2026 (3 mos ago)
DPWH contractor code
2400

Where they work

Latest 25 from a total of 359 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
25M001993 mos agoPREVENTIVE MAINTENANCE - SIMUAY LANDASAN- PARANG ROAD (S01761MN) K1868+000-K1872+000, SULTAN MASTURA, MAGUINDANAO DEL NORTEGAA 2025 OO-1On-GoingRegion XII₱192.9M
25LG01028 mos agoCONSTRUCTION OF ROAD, BARANGAY PINTATAGAN TO BARANGAY MARAGATAS, PHASE 2, BANAYBANAY, DAVAO ORIENTALGAA 2025 SSPOn-GoingDavao Oriental 2nd DEO₱143.2M
25FF00599 mos ago002;PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM-CONST. OF REVETMENT ALONG PENAFRANCIA CREEK,UPSTREAM PALESTINA PILI CAMARINES SURGAA 2025 OO-2On-GoingCamarines Sur 3rd DEO₱84.0M
24IC00489 mos agoCONSTRUCTION OF NICA BUILDING, GOVERNMENT CENTER, PALO, LEYTEGAA 2024 SSPOn-GoingLeyte 1st DEO₱43.1M
24IC02389 mos agoCONSTRUCTION OF BUREAU OF FIRE PROTECTION REGIONAL OFFICE 8 BUILDING, GOVERNMENT CENTER, PALO, LEYTEUnprogrammed Appropriations 2024On-GoingLeyte 1st DEO₱83.9M
25HA011310 mos agoCONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY WEST POBLACION, ALBURQUERQUE, BOHOLGAA 2025 SSPOn-GoingBohol 1st DEO₱98.8M
25F0056110 mos agoCONSTRUCTION OF EVACUATION CENTERS - REGION V :BRGY. GABOC, MERCEDES, CAMARINES NORTE, BRGY. GABOC, MERCEDES, CAMARINES NORTEGAA 2025 LS ItemizationOn-GoingRegion V₱45.8M
25LA00511 yr agoCONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY ELIZALDE, MACO, DAVAO DE OROGAA 2025 SSPOn-GoingDavao de Oro 1st DEO₱3.0M
25NH01191 yr 1 mo agoCONSTRUCTION/IMPROVEMENT OF DRAINAGE BARANGAY TELAJE, TANDAG CITY, SURIGAO DEL SURGAA 2025 SSPCompletedSurigao del Sur 1st DEO₱39.2M
25M002301 yr 2 mo agoPREVENTIVE MAINTENANCE - DAVAO-COTABATO ROAD (JCT. DIGOS - COTABATO SECTION) (SO1753MNH) K1719+000 - K1721+000, SULTAN KUDARAT, MAGUINDANAO DEL NORTEGAA 2025 OO-1On-GoingRegion XII₱93.6M
25K004291 yr 2 mo agoSTRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS, REGION X, SALAY, MISAMIS ORIENTALGAA 2025 LS ItemizationOn-GoingRegion X₱48.0M
25F001771 yr 3 mo agoORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0312+400-K0312+574, K0312+615-K0313+739, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT)RoadsOn-GoingRegion V₱108.2M
25F002411 yr 3 mo agoORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0254+047-K0255+287, K0255+325-K0255+580, STA. ELENA, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT)GAA 2025 OO-1On-GoingRegion V₱142.5M
25GK01331 yr 5 mo agoPREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD K0049 + 366 - K0050 + 616, K0081 + 558 - K0081+842, K0085 + 487 - K0086 + 358GAA 2025 OO-1CompletedNegros Occidental 1st DEO₱142.5M
25KH00741 yr 5 mo agoCONSTRUCTION OF ACCESS ROAD, BARANGAY BAIKINGON, CAGAYAN DE ORO CITYGAA 2025 SSPOn-GoingCagayan de Oro City 1st DEO₱4.9M
25LI00171 yr 8 mo agoCONSTRUCTION OF REVETMENT ALONG SAUG RIVER LEADING TO LIBUGANON RIVER, (MAYAON BRIDGE SECTION), BARANGAY MAYAON, MONTEVISTA, DAVAO DE OROGAA 2025 OO-2On-GoingDavao de Oro 2nd DEO₱105.2M
24IC01161 yr 10 mo agoRENOVATION AND RECONSTRUCTION OF MULTI-PURPOSE HALL (ACTIVITY BUILDING), VSU TOLOSA CAMPUS, TOLOSA, LEYTEBuildings and FacilitiesOn-GoingLeyte 1st DEO₱39.6M
24KH01151 yr 10 mo agoCONCRETING OF ROAD IN BARANGAY PATAG, CAGAYAN DE ORO CITYUnprogrammed Appropriations 2024On-GoingCagayan de Oro City 1st DEO₱4.8M
24O002121 yr 10 mo agoINCREASE IN CARRYING CAPACITY OF COLLEGE OF MEDICINE, UP MANILA - UNIVERSITY OF THE PHILIPPINES SYSTEMBuildings and FacilitiesOn-GoingNational Capital Region₱13.1M
24M000242 yrs 4 mo agoROAD WIDENING - MARBEL-ALLAH VALLEY-COTABATO RD - K1795+260 - K1796+012, K1796+152 - K1796+872, K1796+872 - K1797+080, K1810+060 - K1811+956, DATU HOFFER, MAGUINDANAO DEL SURGAA 2024 OO-1On-GoingRegion XII₱103.4M
24DO00972 yrs 6 mo agoORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0032+700 - K0033+000RoadsOn-GoingRizal 2nd DEO₱14.1M
24KK00932 yrs 7 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COAST GUARD SUBSTATION), BRGY. 6, BALINGASAG, MISAMIS ORIENTALBuildings and FacilitiesCompletedMisamis Oriental 1st DEO₱4.9M
23KC00433 yrs 4 mo agoROAD WIDENING ALONG SAYRE HIGHWAY - K1443+160-K1443+940, MANOLO FORTICH, BUKIDNONRoads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)CompletedBukidnon 3rd DEO₱67.8M
23KL00253 yrs 8 mo agoOFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - BUTUAN CITY - CAGAYAN DE ORO CITY - ILIGAN CITY RD - K1451+468 - 1454+236RoadsCompletedMisamis Oriental 2nd DEO₱49.0M
22IA00204 yrs 8 mo agoCONSTRUCTION OF SEAWALL, BARANGAY BURABOD, BILIRAN, BILIRAN (11.477479,124.455618, TO 11.477148, 124.456834)Flood Control and DrainageCompletedBiliran DEO₱4.9M

Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.