AACAD CORPORATION
Contractor cd0ae5bec533294d02a0
Overview
PhilGEPS awards
₱105.9M · 19 awards
DPWH contracts
₱112.2M · 17 contracts
Rank by recorded value
#6,863 of 23,487
More info
First record
Nov 4, 2022 (4 yrs ago)
Latest record
Jun 8, 2026 (5 mos ago)
DPWH contractor code
52265
Where they work
Surigao del Sur₱213.2M
Dinagat Islands₱5.0M
Latest 17 from a total of 17 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 26NI0015 | 5 mos ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO MAHOGANY, BARANGAY TAGPOPORAN, LINGIG, SURIGAO DEL SUR (8.14322, 126.37534)GAA 2026 SSP | On-Going | Surigao del Sur 2nd DEO | ₱4.8M |
| 26NI0016 | 5 mos ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO TAGBOBO, BARANGAY TAGPOPORAN, LINGIG, SURIGAO DEL SUR (8.11812, 126.43104)GAA 2026 SSP | On-Going | Surigao del Sur 2nd DEO | ₱4.8M |
| 26NI0021 | 5 mos ago | JCT. MAHOGANY ROAD LEADING TO TAGPOPORAN BLUE WATER RESORT, STA. 8+650 - STA. 8+761.5, BRGY. TAGPOPORAN, LINGIG, SURIGAO DEL SURGAA 2026 CP | On-Going | Surigao del Sur 2nd DEO | ₱3.7M |
| 25NI0068 | 1 yr 7 mo ago | CONCRETING OF BRGY. SAN VICENTE TO BRGY. TIDMAN FMR, BRGY. SAN VICENTE AND BRGY. TIDMAN, BISLIG CITY & HINATUAN, SURIGAO DEL SURGAA 2025 DA FMR | Completed | Surigao del Sur 2nd DEO | ₱14.5M |
| 25NI0008 | 1 yr 7 mo ago | NRJ - SITIO STA. MARIA ROAD LEADING TO PALO-ALTO WHITE BEACH RESORT, BRGY. PALO ALTO, LINGIG, SURIGAO DEL SURRoads | Completed | Surigao del Sur 2nd DEO | ₱9.5M |
| 24NI0055 | 2 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BAROBO NATIONAL HIGHSCHOOL, BAROBO, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.9M |
| 24NI0008 | 2 yrs 8 mo ago | PACKAGE 3- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LAGO, MUNICIPALITY OF TAGBINA, SURIGAO DEL SUR- CONSTRUCTION OF MULTI-PURPOSE BUILDING,BARANGAY TRINIDAD, MUNICIPALITY OF TAGBINA, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.9M |
| 23NI0071 | 2 yrs 11 mo ago | CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY PALO ALTO, LINGIG, SURIGAO DEL SURWater Provision and Storage | Completed | Surigao del Sur 2nd DEO | ₱9.8M |
| 23NI0058 | 3 yrs 6 mo ago | CONCRETING OF PUROK 5 SITIO ABIHUD, BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, BISLIG CITY, SURIGAO DEL SURRoads | Completed | Surigao del Sur 2nd DEO | ₱15.9M |
| 23NI0013 | 3 yrs 8 mo ago | OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - SURIGAO-DAVAO COASTAL RD - K1465 + 147 - K1465 + 933.50Roads | Completed | Surigao del Sur 2nd DEO | ₱12.2M |
| 23NI0032 | 3 yrs 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BOGAC DISTRICT, BARANGAY MANGAGOY, BISLIG CITY, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.9M |
| 23NI0035 | 3 yrs 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK TAW-AGA, BARANGAY SALVACION, LINGIG, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.0M |
| 23NI0006 | 3 yrs 9 mo ago | NRJ - SITIO STA. MARIA ROAD LEADING TO PALO-ALTO WHITE BEACH RESORT, BRGY. PALO ALTO, LINGIG, SURIGAO DEL SURRoads | Completed | Surigao del Sur 2nd DEO | ₱2.4M |
| 23NI0023 | 3 yrs 9 mo ago | PACKAGE 8- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CAMBATONG, HINATUAN, SURIGAO DEL SUR- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TARUSAN, HINATUAN, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.9M |
| 23NI0024 | 3 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TAGPOPORAN, LINGIG, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱3.0M |
| 23NI0029 | 3 yrs 9 mo ago | PACKAGE 11- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PALO ALTO, LINGIG, SURIGAO DEL SUR- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LINGIG, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.0M |
| 23NI0034 | 3 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAWIGAN, BISLIG CITY, SURIGAO DEL SURBuildings and Facilities | Completed | Surigao del Sur 2nd DEO | ₱4.0M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.