ADAD ENGINEERING SERVICES AND SUPPLY
Contractor dbbe8a27ccbb28fb309c
Overview
PhilGEPS awards
₱2.22B · 408 awards
DPWH contracts
₱1.12B · 62 contracts
Rank by recorded value
#961 of 23,487
More info
First record
Apr 26, 2011 (15 yrs 6 mo ago)
Latest record
Aug 12, 2026 (3 mos ago)
DPWH contractor code
25477
Where they work
Quezon₱3.33B
Latest 25 from a total of 62 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 24DM0014 | 2 yrs 9 mo ago | NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - ABUYON - BUENAVISTA RD - K0266+320 - K0267+233, SAN NARCISO, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 24DM0018 | 2 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CAMFLORA, SAN ANDRES, QUEZONBuildings and Facilities | Completed | Quezon 3rd DEO | ₱5.0M |
| 24DM0019 | 2 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY IBABANG WASAY, BUENAVISTA, QUEZONBuildings and Facilities | Completed | Quezon 3rd DEO | ₱5.0M |
| 24DM0021 | 2 yrs 9 mo ago | NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT -SECONDARY ROADS - SN FRANCISCO - SN ANDRES - SN NARCISO RD -K0363+000 - K0363+700, SAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 24DM0024 | 2 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SAN PABLO, BUENAVISTA, QUEZONBuildings and Facilities | Completed | Quezon 3rd DEO | ₱5.0M |
| 24DM0056 | 2 yrs 9 mo ago | ASSET PRESERVATION PROGRAM - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0365 + 190 - K0365 + 700, SAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 24DM0064 | 2 yrs 9 mo ago | NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - CATANAUAN - BUENAVISTA RD - K0279+100 - K0279+900, BUENAVISTA, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 24DM0069 | 2 yrs 9 mo ago | ASSET PRESERVATION PROGRAM - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MSR JCT-LOPEZ-BUENAVISTA RD - K0239 + 750 - K0240 + 575, BUENAVISTA, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 23DM0096 | 3 yrs 6 mo ago | CONSTRUCTION OF ACCESS ROAD, BARANGAY POBLACION, SAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱19.6M |
| 23DM0069 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING), SAN ANDRES ELEMENTARY SCHOOL, BRGY. POBLACION, SAN ANDRES, QUEZONBuildings and Facilities | Completed | Quezon 3rd DEO | ₱19.8M |
| 23DM0007 | 3 yrs 8 mo ago | ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - SN FRANCISCO - SN ANDRES - SN NARCISO RD - K0366 + 630 - K0368 + 000, SAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱28.7M |
| 23DL0089 | 3 yrs 8 mo ago | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS 4. CONSTRUCTION OF FLOOD CONTROL AND DRAINAGE STRUCTURE ALONG PIPISIK RIVFlood Control and Drainage | Completed | Quezon 4th DEO | ₱44.1M |
| 22DM0135 | 4 yrs 7 mo ago | SIPAG - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN ANDRES BUILDING, BARANGAY POBLACION, SAN ANDRES, QUEZONSAN ANDRES, QUEZONBuildings and Facilities | Completed | Quezon 3rd DEO | ₱9.8M |
| 22DM0144 | 4 yrs 7 mo ago | CONCRETING OF BRGY. HINGUIWIN FMR, BRGY. HINGUIWIN, PADRE BURGOS, QUEZONPADRE BURGOS, QUEZONRoads | Completed | Quezon 3rd DEO | ₱11.9M |
| 22DM0084 | 4 yrs 7 mo ago | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF ROAD, SITIO SIGARAS TO SITIO YUGNO, BARANGAY CAMFLORA, SAN ANRoads | Completed | Quezon 3rd DEO | ₱24.5M |
| 21DM0066 | 4 yrs 7 mo ago | CONSTRUCTION OF DRAINAGE OF BRGY. POBLACIONSAN ANDRES, QUEZONFlood Control and Drainage | Completed | Quezon 3rd DEO | ₱9.8M |
| 22DL0177 | 4 yrs 7 mo ago | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES 1. CONSTRUCTION OF EVACUATION CENTER, BARANGAY TABING DAGAT, GUMACA, QUEZONBuildings and Facilities | Completed | Quezon 4th DEO | ₱9.8M |
| 22DM0106 | 4 yrs 7 mo ago | CONSTRUCTION OF ROAD, SITIO CENTRAL 2 - SITIO BADYAWA, BRGY. DOONGAN ILAYA, CATANAUAN, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 22DM0100 | 4 yrs 8 mo ago | EMERGENCY RESPONSE CENTER (COMMAND CENTER) AT BARANGAY POBLACION, SAN ANDRES, QUEZONSAN ANDRES, QUEZONBuildings and Facilities | Completed | Quezon 3rd DEO | ₱19.6M |
| 22DL0070 | 4 yrs 8 mo ago | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL AND DRAINAGE STRUCTURE ALONG PIPISIK RIVERFlood Control and Drainage | Completed | Quezon 4th DEO | ₱19.6M |
| 22DM0046 | 4 yrs 9 mo ago | CONSTRUCTION OF ROAD, TAGBACAN ILAYA- TAGBACAN SILANGAN, CATANAUAN, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 22DM0049 | 4 yrs 9 mo ago | CONSTRUCTION OF ROAD, BRGY. CAMFLORA, SAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱9.8M |
| 21DM0055 | 5 yrs 7 mo ago | CONCRETING OF PUNTA ARENA ROAD, BARANGAY TALISAYSAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱5.0M |
| 20DL0244 | 5 yrs 10 mo ago | FY 2020 NATIONAL DISASTER RISK REDUCTION AND MANAGEMENT FUND (CALAMITY FUND), REHABILITATION OF FLOOD CONTROL AND ROAD PROJECTS IN QUEZON: A.)REPAIR/REHABILITATION/RECONSTRUCTION OF FLOOD CONTROL AND DRAINAGE STRUCTURE ALONG PIPISIK RIVER, BARANGAY PIPISIFlood Control and Drainage | Completed | Quezon 4th DEO | ₱17.7M |
| 20DM0062 | 6 yrs 3 mo ago | CONCRETING OF SITIO GUINUHUAN TO SITIO TAMNAO GAMAY, BRGY. CAMFLORA FMR, BRGY. CAMFLORA, SAN ANDRES, QUEZONRoads | Completed | Quezon 3rd DEO | ₱24.9M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.