Project 22DM0144

DPWH infrastructure contract
Contract ID:
22DM0144
Fingerprint:
8c2970059f2f1c…e42ca85079 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 7, 2022 (4 yrs 7 mo ago) · Target/actual end Nov 18, 2022
Description:
CONCRETING OF BRGY. HINGUIWIN FMR, BRGY. HINGUIWIN, PADRE BURGOS, QUEZONPADRE BURGOS, QUEZON
Category:
Roads
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contractor:
ADAD ENGINEERING SERVICES AND SUPPLY · DPWH contractor code 25477
As listed: ADAD ENGINEERING SERVICES & SUPPLY
Contract amount:
₱11,940,000.00 (₱11.9M)
Funding source:
Outside Infra - GAA 2022 DA FMR
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
b32e82ac2f9b…Mar 23, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 3RD ED₱11,576,947.33

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DM0175Jan 14, 2026CONSTRUCTION OF SUPER HEALTH CENTERS, PADRE BURGOS BAGONG PILIPINAS HEALTH CENTER, QUEZONOn-Going₱11.9M
25DM0065Mar 3, 2025NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PADRE BURGOS BY- PASS ROAD, QUEZON, PADRE BURGOS, QUEZONOn-Going₱94.6M
25DM0052Feb 12, 2025BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - CABUYAO BR. (B02954LZ) ALONG P BURGOS-POTOTANIN JCT, PADRE BURGOS, QUEZONCompleted₱20.2M
24DM0110Apr 29, 2024CONSTRUCTION OF MULTIPURPOSE BUILDING, BARANGAY RIZAL, MUNICIPALITY OF PADRE BURGOS, QUEZON, PADRE BURGOS, QUEZONCompleted₱5.0M
24DM0092Apr 11, 2024CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BRGY. CABUYAO, PADRE BURGOS, QUEZONCompleted₱49.0M
24D00148Mar 18, 2024FY 2024 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSPADRE BURGOS BY-PASS ROAD, QUEZON (PACKAGE 4)On-Going₱189.1M
24DM0004Feb 14, 2024ACCESS ROAD LEADING TO HINGUIWIN FALLS, BRGY. HINGUIWIN PADRE BURGOS, QUEZONCompleted₱19.3M
24DM0072Feb 14, 2024NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PADRE BURGOS BY-PASS ROAD, PACKAGE 3Completed₱53.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.