ADROIT EJD CONSTRUCTION CORP. (FORMERLY: ADROIT CONSTRUCTION)
Contractor f0a114b5bc536cf8d050
Overview
PhilGEPS awards
₱649.7M · 84 awards
DPWH contracts
₱1.88B · 220 contracts
Rank by recorded value
#1,230 of 23,487
More info
First record
Mar 7, 2016 (10 yrs 8 mo ago)
Latest record
Jul 8, 2026 (4 mos ago)
DPWH contractor code
11169
Where they work
Latest 25 from a total of 220 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 26CE0006 | 4 mos ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS, SN JOSE-LUPAO RD - K0168 + 964 - K0169 + 782, K0169 + 823 - K0170 + 000GAA 2026 OO-1 | On-Going | Nueva Ecija 1st DEO | ₱31.4M |
| 26CE0014 | 4 mos ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0156 + 300 - K0157 + 170, K0158 + 000 - K0158 + 580GAA 2026 OO-1 | On-Going | Nueva Ecija 1st DEO | ₱33.0M |
| 26CE0015 | 4 mos ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0173 + 000 - K0174 + 000GAA 2026 OO-1 | On-Going | Nueva Ecija 1st DEO | ₱27.0M |
| 25CE0160 | 1 yr 4 mo ago | CONSTRUCTION OF BOX CULVERT, BARANGAY VILLA LABRADOR, RIZAL, NUEVA ECIJAFlood Control and Drainage | Completed | Nueva Ecija 1st DEO | ₱4.9M |
| 25CE0197 | 1 yr 4 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DEL PILAR, RIZAL, NUEVA ECIJAGAA 2025 SSP | Completed | Nueva Ecija 1st DEO | ₱3.9M |
| 25CE0198 | 1 yr 4 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY MAGSAYSAY, TALUGTUG, NUEVA ECIJAGAA 2025 SSP | Completed | Nueva Ecija 1st DEO | ₱4.9M |
| 25CE0204 | 1 yr 4 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALIGAYA ES, BARANGAY MALIGAYA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJABuildings and Facilities | Completed | Nueva Ecija 1st DEO | ₱3.0M |
| 25CE0206 | 1 yr 4 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN FELIPE, SCIENCE CITY OF MUÑOZ, NUEVA ECIJAGAA 2025 SSP | Completed | Nueva Ecija 1st DEO | ₱4.9M |
| 25CE0226 | 1 yr 4 mo ago | CONCRETING OF ROAD, PALASAPAS, BARANGAY MANICLA, SAN JOSE CITY, NUEVA ECIJAGAA 2025 SSP | Completed | Nueva Ecija 1st DEO | ₱9.7M |
| 25CE0212 | 1 yr 5 mo ago | CONSTRUCTION OF SLOPE PROTECTION, BALIWAG BRIDGE ALONG MUÑOZ-LUPAO ROAD, BRGY. AGUPALO WESTE, LUPAO NUEVA ECIJAGAA 2025 SSP | Completed | Nueva Ecija 1st DEO | ₱24.5M |
| 25CE0280 | 1 yr 7 mo ago | CONCRETING OF BRGY. PACO ROMAN FMR, BRGY. PACO ROMAN, RIZAL, NUEVA ECIJAGAA 2025 DA FMR | Completed | Nueva Ecija 1st DEO | ₱14.8M |
| 25CE0256 | 1 yr 7 mo ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0136 + 000 - K0137 + 000Roads | Completed | Nueva Ecija 1st DEO | ₱14.7M |
| 25CE0098 | 1 yr 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY VILLA FLORESTA, SAN JOSE CITY, NUEVA ECIJARoads | Completed | Nueva Ecija 1st DEO | ₱9.8M |
| 25CE0109 | 1 yr 7 mo ago | REHABILITATION OF ROAD, BARANGAY SANTA BARBARA TO BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJARoads | Completed | Nueva Ecija 1st DEO | ₱9.7M |
| 25CE0222 | 1 yr 8 mo ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, MUÑOZ-LUPAO RD - K0147 + 347 - K0147 + 574, K0147 + 589 - K0149 + 000Roads | Completed | Nueva Ecija 1st DEO | ₱23.2M |
| 25CE0223 | 1 yr 8 mo ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, MUÑOZ-LUPAO RD - K0149 + 000 - K0149 + 972, K0150 + 069 - K0151 + 000Roads | Completed | Nueva Ecija 1st DEO | ₱27.3M |
| 25CE0058 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY PUTLAN, CARRANGLAN, NUEVA ECIJAGAA 2025 OO-2 | Completed | Nueva Ecija 1st DEO | ₱26.1M |
| 25CE0010 | 1 yr 9 mo ago | CONSTRUCTION OF ROAD, BARANGAY PALUSAPIS, SCIENCE CITY OF MUÑOZ, NUEVA ECIJARoads | Completed | Nueva Ecija 1st DEO | ₱14.6M |
| 25CE0011 | 1 yr 9 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, AGBANNAWAG ELEMENTARY SCHOOL, BARANGAY AGBANNAWAG, RIZAL, NUEVA ECIJABuildings and Facilities | Completed | Nueva Ecija 1st DEO | ₱3.4M |
| 25CE0042 | 1 yr 9 mo ago | REHABILITATION OF ROAD, BARANGAY VILLA MARINA, SAN JOSE CITY, NUEVA ECIJARoads | Completed | Nueva Ecija 1st DEO | ₱9.7M |
| 25CE0044 | 1 yr 9 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LIGAYA, LLANERA, NUEVA ECIJABuildings and Facilities | Completed | Nueva Ecija 1st DEO | ₱2.5M |
| 25CE0067 | 1 yr 9 mo ago | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT CORDERO CIS, LUPAO, NUEVA ECIJAFlood Control and Drainage | Completed | Nueva Ecija 1st DEO | ₱9.7M |
| 25CE0101 | 1 yr 9 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, CARIDAD NORTE ELEMENTARY SCHOOL, BARANGAY CARIDAD NORTE, LLANERA, NUEVA ECIJABuildings and Facilities | Completed | Nueva Ecija 1st DEO | ₱3.5M |
| 25CE0119 | 1 yr 9 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, ENCARNACION ELEMENTARY SCHOOL, BARANGAY SANTO NIÑO 1ST, SAN JOSE CITY, NUEVA ECIJABuildings and Facilities | Completed | Nueva Ecija 1st DEO | ₱3.0M |
| 25CE0169 | 1 yr 9 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALASIN, SAN JOSE CITY, NUEVA ECIJABuildings and Facilities | Completed | Nueva Ecija 1st DEO | ₱2.0M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.