JORMAND CONSTRUCTION & SUPPLY
Contractor f1762aa017262f9aefec
Overview
PhilGEPS awards
₱1.91B · 65 awards
DPWH contracts
₱1.35B · 39 contracts
Rank by recorded value
#986 of 23,487
More info
First record
Mar 13, 2020 (6 yrs 8 mo ago)
Latest record
Jul 10, 2026 (4 mos ago)
DPWH contractor code
40760
Where they work
Albay₱3.26B
Latest 25 from a total of 39 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 26FA0003 | 4 mos ago | ROAD WIDENING-SECONDARY ROADS-DAANG MAHARLIKA JCT-LEGAZPI-STO. DOMINGO-TABACO-CAMARINES SUR BDRY. ROAD-K0549+ 825- K0550+ 809GAA 2026 OO-1 | On-Going | Albay 1st DEO | ₱52.8M |
| 25FA0039 | 1 yr 1 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) CONVERTIBLE TO EVACUATION CENTER AT SAN ISIDRO, STO. DOMINGO, ALBAYGAA 2025 SSP | On-Going | Albay 1st DEO | ₱11.9M |
| 25FA0034 | 1 yr 1 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT BESIDE THE NEW LEGISLATIVE BUILDING), KARANGAHAN BOULEVARD, TABACO CITY, ALBAYGAA 2025 SSP | On-Going | Albay 1st DEO | ₱14.8M |
| 25FA0019 | 1 yr 7 mo ago | CONSTRUCTION OF SEAWALL, BARANGAY 3, MALILIPOT, ALBAY (PHASE II)GAA 2025 OO-2 | Completed | Albay 1st DEO | ₱67.5M |
| 25FA0021 | 1 yr 7 mo ago | ROAD WIDENING-SECONDARY RDS.: DAANG MAHARLIKA-JCT-LEG.-STO. DOMINGO-TABACO-CAM. SUR BDRY. RD. K0550+809-K0551+413GAA 2025 OO-1 | Completed | Albay 1st DEO | ₱48.3M |
| 24FA0063 | 2 yrs 1 mo ago | CONSTRUCTION OF 2STY6CL, OGOB ELEMENTARY SCHOOL, MALINAO, ALBAYGAA 2024 DepEd BEFF | On-Going | Albay 1st DEO | ₱35.7M |
| 24FA0052 | 2 yrs 1 mo ago | CLUSTER 11 - CONSTRUCTION/IMPROVEMENT OF VARIOUS ACCESSS ROADS IN THE FIRST DISTRICT OF ALBAYGAA 2024 CP | Completed | Albay 1st DEO | ₱58.8M |
| 24FA0047 | 2 yrs 3 mo ago | CLUSTER 8-ROAD WIDENING-SECONDARY ROADS ALONG DAANG MAHARLIKA JCT.-LEGAZPI-STO. DOMINGO-TABACO-CAM. SUR BDRY. ROAD AND ALONG LIGAO-TABACO ROADGAA 2024 OO-1 | Completed | Albay 1st DEO | ₱34.3M |
| 23FA0091 | 2 yrs 4 mo ago | CLUSTER 29- CONST. OF ELEM. SCHOOL BLDGS. (CLASSROOMS) IN THE FIRST DISTRICT OF ALBAYBuildings and Facilities | Completed | Albay 1st DEO | ₱41.4M |
| 24FA0029 | 2 yrs 4 mo ago | CLUSTER 1- REHAB./CONST./EXTENSION OF RIVER CONTROL PROTECTING BASUD BRIDGE,STO. DOMINGO. ALBAY AND BRGY. 13, BACACAY, ALBAYGAA 2024 OO-2 | On-Going | Albay 1st DEO | ₱73.0M |
| 24FA0005 | 2 yrs 8 mo ago | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: TIWI BY-PASS ROAD (ALTERNATE ROUTE), ALBAYRoads | Completed | Albay 1st DEO | ₱49.0M |
| 24FA0001 | 2 yrs 8 mo ago | CONSTRUCTION OF MISSING LINKS/NEW ROADS, TABACO CITY-MALINAO-BUHI-IRIGA ROAD, ALBAYRoads | Completed | Albay 1st DEO | ₱49.0M |
| 24FA0010 | 2 yrs 8 mo ago | CONSTRUCTION OF JOROAN RIVER CONTROL (DOWNSTREAM), TIWI, ALBAYFlood Control and Drainage | Completed | Albay 1st DEO | ₱39.2M |
| 24FA0007 | 2 yrs 9 mo ago | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: LEGAZPI-STO. DOMINGO-BACACAY-TABACO TRAMO ROAD, ALBAYRoads | Completed | Albay 1st DEO | ₱49.0M |
| 24FA0009 | 2 yrs 9 mo ago | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS: ACCESS ROADS LEADING TO KARANGAHAN BOULEVARD, TABACO CITY, ALBAYRoads | Completed | Albay 1st DEO | ₱47.0M |
| 23FA0072 | 2 yrs 11 mo ago | CONSTRUCTION OF SOLAR WATER SYSTEM, TIWI, ALBAYWater Provision and Storage | Completed | Albay 1st DEO | ₱9.8M |
| 23FA0074 | 2 yrs 11 mo ago | CONSTRUCTION OF SOLAR WATER SYSTEM AT SAN MIGUEL NATIONAL HIGH SCHOOL, BRGY. SAN MIGUEL, TABACO CITY, ALBAYWater Provision and Storage | Completed | Albay 1st DEO | ₱5.0M |
| 23FA0050 | 3 yrs 1 mo ago | CLUSTER 15-CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT CONVERTIBLE INTO AN EVACUATION CENTER) AT TABACO CITY, BACACAY AND MALILIPOT, ALBAYBuildings and Facilities | Completed | Albay 1st DEO | ₱33.5M |
| 23FA0041 | 3 yrs 5 mo ago | CLUSTER 11- REHAB. OF POBLACION-BACLAYON-VINISITAHAN-SAN PEDRO-PILI ROAD, BACACAY, ALBAY & CONST. OF BACLAYON BRGY. ROAD AT PUROK 7, BACACAY, ALBAYRoads | Completed | Albay 1st DEO | ₱34.4M |
| 23FA0032 | 3 yrs 6 mo ago | CLUSTER 4- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS IN THE FIRST DISTRICT OF ALBAYRoads | Completed | Albay 1st DEO | ₱48.5M |
| 23FA0035 | 3 yrs 6 mo ago | CLUSTER 7- CONST. OF VINISITAHAN FLOOD CONTROL (DOWNSTREAM) ALONG BACLAYON RIVER, BACACAY, ALBAY AND CONST. OF BARANGHAWON FLOOD MITIGATION STRUCTURE, TABACO CITY, ALBAYFlood Control and Drainage | Completed | Albay 1st DEO | ₱46.1M |
| 23FA0030 | 3 yrs 6 mo ago | CLUSTER 2- CONSTRUCTION OF RIVER CONTROL/FLOOD MITIGATION AT LIBOD, MALINAO; TAYHI RIVER BARANGAY CORMIDAL, TABACO CITY & AT BARANGAY 7, BACACAY, ALBAYFlood Control and Drainage | Completed | Albay 1st DEO | ₱30.7M |
| 23FA0006 | 3 yrs 8 mo ago | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: LEGAZPI-STO. DOMINGO-BACACAY-TABACO TRAMO ROAD, BACACAY, ALBAYRoads | Completed | Albay 1st DEO | ₱39.2M |
| 23FA0008 | 3 yrs 8 mo ago | CONSTRUCTION OF MISSING LINKS/NEW ROADS: TABACO CITY-MALINAO-BUHI-IRIGA ROAD, MALINAO, ALBAYRoads | Completed | Albay 1st DEO | ₱39.2M |
| 23FA0011 | 3 yrs 8 mo ago | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: SAN LORENZO-SALVACION-FATIMA-TAGAS-SAN ROQUE-TABACO WHARF ROAD, TABACO CITY, ALBAYRoads | Completed | Albay 1st DEO | ₱39.2M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.