FY2026 GAA: ₱6.79T
PisoScan

SO CONSTRUCTION

Contractor fa63a3fd2bd0b534a1dc

Overview

PhilGEPS awards
₱1.24B · 181 awards
DPWH contracts
₱856.6M · 89 contracts
Rank by recorded value
#1,419 of 23,487

More info

First record
May 29, 2009 (17 yrs 5 mo ago)
Latest record
Jan 19, 2026 (9 mos ago)
DPWH contractor code
17714

Where they work

Aurora₱2.09B
Latest 25 from a total of 89 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
25CN02139 mos agoLAST MILE SCHOOLS PROGRAM - GALINTUJA ELEMENTARY SCHOOL, MARIA AURORA, AURORAGAA 2025 DepEd Last Mile Schools ProgramOn-GoingAurora DEO₱9.9M
25CN01841 yr 4 mo agoCONSTRUCTION OF SCHOOL BUILDING ABUNGAN ELEMENTARY SCHOOL, DINGALAN, AURORAGAA 2025 DEPED BEFFCompletedAurora DEO₱9.8M
25CN00891 yr 4 mo agoCONSTRUCTION OF ROAD, BARANGAY PALEG, DINALUNGAN, AURORAGAA 2025 SSPCompletedAurora DEO₱34.3M
25CN01651 yr 4 mo agoREHABILITATION OF MULTI - PURPOSE BUILDING, SAN LUIS CENTRAL ELEMENTARY SCHOOL, SAN LUIS, AURORAGAA 2025 SSPOn-GoingAurora DEO₱4.8M
25CN00921 yr 7 mo agoCONSTRUCTION OF ROAD, BARANGAY SAN JOSE, MARIA AURORA, AURORAGAA 2025 SSPCompletedAurora DEO₱7.6M
25CN00601 yr 8 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ZARAH ELEMENTARY SCHOOL, BARANGAY ZARAH, SAN LUIS, AURORAGAA 2025 SSPCompletedAurora DEO₱5.0M
25CN01071 yr 8 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY LABOY, DIPACULAO, AURORAGAA 2025 SSPCompletedAurora DEO₱9.7M
24CN00842 yrs 2 mo agoCONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. LOBOT, DIPACULAO, AURORAGAA 2024 SSPOn-GoingAurora DEO₱19.4M
24CN02092 yrs 3 mo agoCONCRETING OF BRGY. NIPOO FMR PHASE II, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 DA FMRCompletedAurora DEO₱25.9M
24CN01962 yrs 4 mo agoCONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SUGUIT NATIONAL HIGH SCHOOL, BRGY. SUGUIT, MARIA AURORA, AURORABuildings and FacilitiesCompletedAurora DEO₱4.9M
24CN02002 yrs 4 mo agoCONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN LUIS CENTRAL SCHOOL, BRGY. 1, SAN LUIS, AURORABuildings and FacilitiesCompletedAurora DEO₱4.9M
24CN01212 yrs 5 mo agoCONSTRUCTION OF ROAD, DIAT, MARIA AURORA, AURORARoadsCompletedAurora DEO₱11.9M
24CN01452 yrs 5 mo agoCONSTRUCTION OF HIGHWAY TO DILEBSONG ROAD, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 SSPCompletedAurora DEO₱19.8M
24CN00402 yrs 6 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DICABASAN ELEMENTARY SCHOOL, BARANGAY DICABASAN, DILASAG, AURORAGAA 2024 SSPCompletedAurora DEO₱6.4M
24CN01832 yrs 6 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. DIANED, DIPACULAO, AURORABuildings and FacilitiesCompletedAurora DEO₱9.7M
24CN00582 yrs 6 mo agoCONSTRUCTION OF ROAD, BRGY. NIPOO, DINALUNGAN, AURORAGAA 2024 SSPCompletedAurora DEO₱22.0M
24CN00632 yrs 6 mo agoCONSTRUCTION OF ROAD, SO. DILAGDES, BRGY. MAPALAD, DINALUNGAN, AURORAGAA 2024 SSPCompletedAurora DEO₱34.7M
24CN00642 yrs 6 mo agoCONSTRUCTION OF ROAD, SO. LIYOG, BRGY. MAPALAD, DINALUNGAN, AURORAGAA 2024 SSPCompletedAurora DEO₱34.7M
24CN01352 yrs 6 mo agoCONSTRUCTION OF ROAD, BRGY. PALEG, DINALUNGAN, AURORARoadsCompletedAurora DEO₱9.6M
24CN01442 yrs 7 mo agoCONSTRUCTION OF NIPOO - TAMBALONGAN ROAD, BRGY. NIPOO, DINALUNGAN, AURORARoadsCompletedAurora DEO₱19.2M
24CN00392 yrs 9 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DIARABASIN NATIONAL HIGH SCHOOL, BARANGAY DIARABASIN, DIPACULAO, AURORABuildings and FacilitiesCompletedAurora DEO₱6.3M
23CN01343 yrs 4 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMERCIAL BUILDING), BALER, AURORABuildings and FacilitiesCompletedAurora DEO₱24.5M
23CN01463 yrs 5 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. DIAMAN, MARIA AURORA, AURORABuildings and FacilitiesCompletedAurora DEO₱2.9M
23CN01383 yrs 6 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), STO. TOMAS ELEMENTARY SCHOOL, BRGY. STO. TOMAS, MARIA AURORA, AURORABuildings and FacilitiesCompletedAurora DEO₱3.8M
23CN01473 yrs 7 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH FACILITY), MARIA AURORA, AURORABuildings and FacilitiesCompletedAurora DEO₱14.3M