Project 15JC0120

DPWH infrastructure contract
Contract ID:
15JC0120
Fingerprint:
29b14aec66a41c…5af468b492 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 17, 2016 (10 yrs 7 mo ago) · Target/actual end Nov 10, 2017
Description:
PROPOSED CONSTRUCTION OF MONTIVOH BRIDGE # 2 ALONG SIRAWAI- SIBUCO-LIMPAPA ROAD, ZN
Category:
Bridges-Construction-Concrete, Flood Control/Hydraulics/River Control
Implementing office:
Contractor:
LONG ISLAND BUILDERS & CONSTRUCTION · DPWH contractor code 31730
Contract amount:
₱19,993,890.53 (₱20.0M)
Funding source:
Regular Infra - Bridges-Construction-Concrete, Flood Control/Hydraulics/River Control
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
dab1d96592db…Feb 22, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZN 2ND DEO₱19,993,890.54

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.