Project 16AA0048
DPWH infrastructure contract
Contract ID:
16AA0048
Fingerprint:
ca51780dabe0e8…6503b8f0b3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 25, 2016 (10 yrs 8 mo ago) · Target/actual end Aug 11, 2016
Description:
DAMAGED FC FACILITIES/STRUCTURES UNDER THE LRBFC & SABO PROJ, PAGUDPUD FC, CAUNAYAN RIVER, # CAUNAYA
Category:
Flood Control and Drainage
Implementing office:
DPWH Ilocos Norte 1st DEO · Region I
Contractor:
BLUE MOUNTAIN BUILDERS & GENERAL MDSE.(FOR. BLUE M · DPWH contractor code 34745
Location:
Contract amount:
₱9,288,416.34 (₱9.3M)
Funding source:
Regular Infra - GAA 2016 MFO-2
Budget year:
2016