Project 16C00046
DPWH infrastructure contract
Contract ID:
16C00046
Fingerprint:
fdd4b645c36022…f6694e8725 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 23, 2016 (10 yrs 4 mo ago) · Target/actual end Jan 27, 2019
Description:
NETWORK DEVELOPMENT-CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-WIDENING OF BRIDGES TO MORE THAN 2-LANES, STA. MARIA BRIDGE (BO1654LZ) ALONG STA. MARIA NORZAGARAY ROAD, BULACAN 4TH LEGISLATIVE DISTRICT, PROVINCE OF BULACAN
Category:
GAA 2016 MFO-1
Implementing office:
DPWH Region III · Region III
Contractor:
525 CONSTRUCTION (28532) / M.G. SALAZAR CONSTRUCTION CORP. (FOR. M.G. SALAZAR · DPWH contractor code 4072
Location:
Not stated in the source
Contract amount:
₱57,845,849.05 (₱57.8M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016