Project 16CA0055
DPWH infrastructure contract
Contract ID:
16CA0055
Fingerprint:
a6e7f3ea9d00cf…7d47b9844e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 24, 2016 (10 yrs ago) · Target/actual end Jan 19, 2017
Description:
CONCRETING OF BARANGAY SAN SIMON FARM TO MARKET ROAD, BARANGAY SAN SIMON, DINALUPIHAN, BATAAN
Category:
Roads
Implementing office:
DPWH Bataan 1st DEO · Region III
Contractor:
AS MACHA CONSTRUCTION AND TRADING · DPWH contractor code 36878
Location:
Contract amount:
₱1,934,280.00 (₱1.9M)
Funding source:
Outside Infra - GAA 2016 DA Farm-to-Market Roads
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c66bebe72406… | Sep 27, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATAAN 1ST DEO | ₱1,934,280.00 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.