Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16CF0141

DPWH infrastructure contract
Contract ID:
16CF0141
Fingerprint:
83734ed574c015…1e4da6b978 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 15, 2016 (9 yrs 10 mo ago) · Target/actual end Jun 7, 2017
Description:
CONSTRUCTION OF A 2STY10CL SCHOOL BUILDING, BONGABON NHS, BONGABON, NUEVA ECIJA 3RD LD - CONSTRUCTION OF CLASSROOMS
Category:
Buildings and Facilities
Implementing office:
Contractor:
FAR EAST EAGLE CONSTRUCTION AND DEVELOPMENT · DPWH contractor code 14583
Contract amount:
₱12,612,915.66 (₱12.6M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016