Project 16GB0176
DPWH infrastructure contract
Contract ID:
16GB0176
Fingerprint:
ec348c1d69ac15…074c641084 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 25, 2017 (9 yrs 5 mo ago) · Target/actual end Dec 20, 2017
Description:
CONSTRUCTION OF REVETMENT AT SIBALOM RIVER ALONG SAN REMIGIO-BUGO ROAD, SAN REMIGIO, ANTIQUE
Category:
Flood Control and Drainage
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
CLIFFORD CONSTRUCTION CORPORATION · DPWH contractor code 3724
Location:
Contract amount:
₱32,499,250.00 (₱32.5M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.