Project 16GD0003
DPWH infrastructure contract
Contract ID:
16GD0003
Fingerprint:
57ebf6f4509adf…1a185b840f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 25, 2016 (10 yrs 8 mo ago) · Target/actual end Oct 15, 2016
Description:
CONSTRUCTION OF OLD GUIA SPILLWAY, MAAYON, CAPIZ (CONCRETING OF APPROACHES)
Category:
Flood Control and Drainage
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
WILLIAM UY CONSTRUCTION · DPWH contractor code 6991
Location:
Contract amount:
₱13,738,879.39 (₱13.7M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9d7f2c0aff23… | Feb 12, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO | ₱13,738,987.97 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.