Project 16Z00009
DPWH infrastructure contract
Contract ID:
16Z00009
Fingerprint:
24ac420ea8b9cc…0d467aaf0c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 8, 2018 (8 yrs 6 mo ago) · Target/actual end Feb 23, 2023
Description:
BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON CONTRACT PACKAGE 1B
Category:
Bridges
Implementing office:
DPWH Bridges Management Cluster · Central Office
Contractor:
R. D. INTERIOR JUNIOR CONSTRUCTION · DPWH contractor code 6483
As listed: R.D. INTERIOR JUNIOR CONSTRUCTION
Contract amount:
₱690,413,838.91 (₱690.4M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d0759c659096… | Jan 5, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MAIN | ₱708,059,664.86 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BC0058 | Jun 11, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF CAGAYAN RIVER REVETMENT 5 AL | Completed | ₱96.3M |
| 25BC0020 | Apr 11, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER BANK PROTECTION, ZINUNDUNGAN RIVER IRRIGATION SY | On-Going | ₱14.4M |
| 25BC0001 | Mar 28, 2025 | ORGANIZATION OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS _ JCT. LOGAC-LASAM-GAGABUTAN RD - K0716+000-K0718+000, K0719+000-K0721+460, K0721+598-K0724+000 | Completed | ₱20.1M |
| 25BC0038 | Mar 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) SAN PEDRO-MAGSAYSAY-CABATACAN WEST BARA | Completed | ₱12.2M |
| 25BC0023 | Mar 7, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF ALANNAY FLOOD CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER, LAS | Completed | ₱48.9M |
| 25BC0022 | Feb 28, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS: CONSTRUCTION OF MALINTA FLOOD CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER, BARA | Completed | ₱49.0M |
| 25BC0039 | Feb 28, 2025 | CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - AGGUNETAN-TAGAO-VIGA BARANGAY ROAD TO JCT. LOGAC-LASAM-GAGABUTAN ROAD CONN | Completed | ₱5.7M |
| 25BC0042 | Feb 28, 2025 | CSSP-CONS/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - CABATACAN EAST BARANGAY ROAD TO JCT. LOGAC-LASAM-GAGABUTAN ROAD CONNECTING TO C | On-Going | ₱28.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.