FY2026 GAA: ₱6.79T
PisoScan

Project 17BF0195

DPWH infrastructure contract
Contract ID:
17BF0195
Fingerprint:
f2b5cdc8885655…1c63910e4c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 20, 2018 (8 yrs 2 mo ago) · Target/actual end Mar 28, 2019
Description:
CONSTRUCTION OF ADDITIONAL WARD BUILDING AND COMPLETION OF HOSPITAL BUILDING AT QUEZON COMMUNITY HOSPITAL, QUEZON, ISABELA
Category:
Buildings and Facilities
Implementing office:
Contractor:
ATLANTIC CONSTRUCTION · DPWH contractor code 24232
Contract amount:
₱7,078,180.55 (₱7.1M)
Funding source:
Outside Infra - GAA 2017 DOH HFEP
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fc1a9434744a…Aug 1, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 2ND DEO₱7,078,180.55

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26BF0037Aug 3, 2026ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LAGUINDAY PARALLEL BR. ALONG SANTIAGO-TUGUEGARAO RD, RIZAL KALINGAOn-Going₱56.1M
25BF0104Oct 13, 2025RAINWATER COLLECTOR SYSTEM 1. VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA 2. BURGOS NATIONAL HIGH SCHOOL, BURGOS, ISABELA 3. HARANA ELEMENTARY SCHOOL, LUNA, ISABELA 4. BIMONTON INTEGRATED SCHOOL, MALLIG, ISABELA 5. MANANO ELEMENTARY SCHOOL MAIN, MALLIG,On-Going₱2.5M
25BF0068Aug 6, 2025OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, UPPER CHICO RIVER IRRIGATION SYSTEM, QUEZON, ISABELACompleted₱14.0M
25BF0089Aug 4, 2025CONSTRUCTION OF SCHOOL BUILDING, MINAGBAG INTEGRATED SCHOOL, QUEZON, ISABELACompleted₱4.8M
25BF0076Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JUAN, QUEZON, ISABELACompleted₱5.8M
25BF0078Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BRGY. SAMONTE, QUEZON, ISABELACompleted₱9.6M
25BF0049Jun 30, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TUROD, QUEZON, ISABELAOn-Going₱4.8M
25BF0029Jun 16, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAMONTE, QUEZON, ISABELAOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.