Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17DF0149

DPWH infrastructure contract
Contract ID:
17DF0149
Fingerprint:
40bedd618d9435…149dd7d624 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 12, 2017 (8 yrs 11 mo ago) · Target/actual end Mar 26, 2018
Description:
COMPLETION OF 4STY 12CL SCHOOL BUILDING AT BAYANAN ES; 4STY 16CL AND 3STY 6CL SCHOOL BUILDING AT BACOOR ES; 4STY 8CL SCHOOL BUILDING AT POBLACION ES (BACOOR ANNEX); 4STY 16CL SCHOOL BUILDING AT HABAY ES; 4STY 20CL SCHOOL BUILDING AT QUEENSROW ES; AND 4ST
Category:
GAA 2017 DepEd BEFF
Implementing office:
DPWH Cavite 1st DEO · Region IV-A
Contract amount:
₱38,314,891.45 (₱38.3M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DQ0110Jul 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITEOn-Going₱9.8M
25DQ0111Jul 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITEOn-Going₱9.8M
25DF0158Jul 1, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS,On-Going₱4.8M
25DQ0084Jun 17, 2025CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITEOn-Going₱96.0M
25DQ0085Jun 17, 2025CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITEOn-Going₱98.0M
25DQ0090Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1)On-Going₱98.0M
25DQ0099Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3)On-Going₱98.0M
25DQ0101Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2)On-Going₱98.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.