Project 17DN0163
DPWH infrastructure contract
Contract ID:
17DN0163
Fingerprint:
4579a60981d870…0668c9ff2c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 12, 2017 (8 yrs 10 mo ago) · Target/actual end Oct 7, 2018
Description:
CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM MARCELINO M. SANTOS NHS, ANTIPOLO CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
EASTERN CONSTRUCTION COMPANY, INC. · DPWH contractor code 2225
Location:
Contract amount:
₱17,582,448.66 (₱17.6M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017