Project 17FB0176
DPWH infrastructure contract
Contract ID:
17FB0176
Fingerprint:
f38cf29b0084b1…43000eff79 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 3, 2018 (8 yrs 10 mo ago) · Target/actual end May 12, 2018
Description:
CONSTRUCTION OF CLASSROOMS 2STY4CL BARIW ES, CAMALIG, ALBAY
Category:
Buildings and Facilities
Implementing office:
DPWH Albay 2nd DEO · Region V
Contractor:
MARCANT CONSTRUCTION & SUPPLY · DPWH contractor code 34118
As listed: MARCANT CONSTRUCTION AND SUPPLY
Contract amount:
₱9,790,430.00 (₱9.8M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ea271abe5cff… | Dec 15, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ALBAY 2ND DEO | ₱9,790,430.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24FB0243 | Jul 30, 2025 | DEPED BASIC EDUCATIONAL FACILITY FUND -CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING AT TUMPA ELEMENTARY SCHOOL, BARANGAY TUMPA, CAMALIG, ALBAY | On-Going | ₱19.3M |
| 25F00163 | Jul 17, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD DIKE STRUCTURE ALONG QUIRANGAY RIVER, PACKAGE 1, BARANGAY QUIRANGAY , CA | On-Going | ₱69.3M |
| 25FB0117 | Jul 16, 2025 | CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTINGMAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF DIKE, BARANGAY SUA, CAMALIG, ALBAY | On-Going | ₱93.6M |
| 25F00145 | Jul 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF RIVER BANK PROTECTION WORKS AND DRAINAGE STRUCTURE, DOWNSTREAM SECTION, BAR | On-Going | ₱50.9M |
| 25F00287 | Jul 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD DIKE STRUCTURE ALONG BARANGAY LIBOD-BARANGAY BARIW, CAMALIG, ALBAY, CAMA | On-Going | ₱29.0M |
| 25F00098 | Jun 3, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0490+201-K0490+437, POLANGUI, ALBAY (3RD LEGISLATIVE DISTRICT) | On-Going | ₱17.8M |
| 25F00142 | May 30, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF FLOOD MITIGATION STRUCTURE, PACKAGE 1, BARANGAY TAGAYTAY, CAMALIG, ALBAY, | On-Going | ₱52.5M |
| 25FB0039 | Apr 18, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DIKE, BARANGAY QUIRANGAY, CAMALIG, ALBAY | On-Going | ₱93.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.