Project 17FN0036
DPWH infrastructure contract
Contract ID:
17FN0036
Fingerprint:
7060dcecc3cc0c…50afd3649f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 25, 2017 (9 yrs 5 mo ago) · Target/actual end Jul 21, 2017
Description:
REBLOCKING OF BARANGAY ROAD AT BRGY. POBLACION ILAOD GOING TO BRGY. APAD, RAGAY, CAM. SUR
Category:
Roads
Implementing office:
DPWH Camarines Sur 1st DEO · Region V
Contractor:
SAINT BERNARD CONSTRUCTION · DPWH contractor code 28368
Location:
Contract amount:
₱4,702,036.00 (₱4.7M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 91724e224a31… | May 10, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH | ₱4,702,036.00 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.