Project 17HB0073
DPWH infrastructure contract
Contract ID:
17HB0073
Fingerprint:
62c027b9783bec…b28ede2527 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 6, 2017 (9 yrs 4 mo ago) · Target/actual end Aug 4, 2017
Description:
(P00145856VS-CW1) - COMPLETION OF MULTI-PURPOSE BUILDING (GINGER PROCESSING CENTER/EVACUATION CENTER), CANDABONG, LOBOC, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 3rd DEO · Region VII
Contractor:
MUANA CONSTRUCTION AND DEVELOPMENT CORP. (FORMERLY · DPWH contractor code 9354
Location:
Contract amount:
₱960,310.00 (₱960.3K)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.