Project 17HB0214

DPWH infrastructure contract
Contract ID:
17HB0214
Fingerprint:
4557a2e619ed83…33273f8cae Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 15, 2018 (8 yrs 9 mo ago) · Target/actual end May 1, 2018
Description:
CONSTRUCTION OF ROXAS PRIMARY SCHOOL (1-STOREY/2 CLASSROOMS, 7.00M X 9.00M UNDER THE LIST OF SCHOOLS WITH URGENT NEED FOR REPLACEMENT & NEW CONSTRUCTION OF CLASSROOMS, BILAR, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 3rd DEO · Region VII
Contractor:
WIL TAN CONSTRUCTION · DPWH contractor code 8622
Contract amount:
₱2,522,545.25 (₱2.5M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3b33f25325a6…Dec 21, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 3RD DEO₱2,522,545.25

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.