Project 17KG0154
DPWH infrastructure contract
Contract ID:
17KG0154
Fingerprint:
d9a4e3b85f45ff…75341cf0c4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 3, 2017 (8 yrs 11 mo ago) · Target/actual end Feb 25, 2018
Description:
CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN KALANGANAN ES, PANTAR, LANAO DEL NORTE
Category:
GAA 2017 DepEd BEFF
Implementing office:
DPWH Lanao del Norte 2nd DEO · Region X
Contractor:
N-ASIACOM BUILDERS · DPWH contractor code 34016
Contract amount:
₱2,550,655.08 (₱2.6M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2bfea133d2fe… | Nov 13, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LANAO DEL NORTE 1S | ₱2,550,655.08 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24K00381 | Sep 26, 2024 | CONSTRUCTION OF SCHOOL BUILDING, RANTIAN ELEMENTARY SCHOOL, BRGY. RANTIAN, BAYANG, LANAO DEL SUR | Completed | ₱9.5M |
| 24K00346 | Aug 12, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MADAYA, MUNICIPALITY OF BINIDAYAN, LANAO DEL SUR | Completed | ₱4.9M |
| 23KG0074 | Sep 15, 2023 | CONSTRUCTION OF 2STY6CL, TAMBO-CADAYONAN ES, PANTAR, LANAO DEL NORTE | Completed | ₱27.8M |
| 23KG0065 | Aug 29, 2023 | CONSTRUCTION OF 1STY3CL, BOWI PS, PANTAR, LANAO DEL NORTE | Completed | ₱10.6M |
| 22KG0102 | Jul 13, 2022 | CONCRETING OF BRGY. LALA PROPER FMR, BRGY. LALA PROPER, LALA, LANAO DEL NORTE | Completed | ₱11.9M |
| 22KG0074 | Jun 7, 2022 | ASSET PRSERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS,SLOPE COLLAPSE AND LANDSLIDE-PRIMARY ROADS,ILIGAN CITY-MARAWI CITY ROAD K1548+130-K1548+220,PANTAR,LANAO DEL NORTE | Completed | ₱9.2M |
| 22KG0034 | Jan 27, 2022 | ASSET PRESERVATION-PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, ILIGAN CITY-MARAWI CITY ROAD, K1550+560-K1550+830, PANTAR, LANAO DEL NORTE | Completed | ₱18.0M |
| 20KG0084 | Dec 17, 2020 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS, ILIGAN CITY-MARAWI CITY ROAD, K1552+539-K1553+955, PANTAR, LANAO DEL NORTE | Completed | ₱32.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.