Project 17KK0221

DPWH infrastructure contract
Contract ID:
17KK0221
Fingerprint:
0ec0bb8bad39b9…44e79c8d87 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 3, 2018 (8 yrs 10 mo ago) · Target/actual end Jan 22, 2018
Description:
COMPLETION OF SCHOOL BUILDING, 2STY 6CL, SALAY NHS, SALAY, MISAMIS ORIENTAL
Category:
Buildings and Facilities
Implementing office:
Contractor:
RYM CONSTRUCTION · DPWH contractor code 12035
Contract amount:
₱264,012.00 (₱264.0K)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
944c18c0e026…Dec 22, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MISAMIS ORIENTAL 1₱264,012.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25K00429Aug 15, 2025STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS, REGION X, SALAY, MISAMIS ORIENTALOn-Going₱48.0M
25KK0056Jul 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM FOR SALAY COMMUNITY COLLEGE), BRGY. POBLACION, SALAY, MISAMIS ORIENTALOn-Going₱49.5M
25KK0068Apr 3, 2025CONCRETING OF BRGY. GASTON FMR, BRGY. GASTON, LAGONGLONG, MISAMIS ORIENTALCompleted₱14.9M
24KK0001Jul 11, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY INOBULAN, SALAY, MISAMIS ORIENTALCompleted₱5.9M
24KK0090May 2, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (CHILD DEVELOPMENT CENTER), PUROK 4, BRGY. LOOC, SALAY, MISAMIS ORIENTALCompleted₱6.9M
24K00073Apr 18, 2024CONST. OF BY-PASS AND DIVERSION ROADS, CLAVERIA-BALINGOAN BY-PASS ROAD, PACKAGE 8, MISAMIS ORIENTALCompleted₱86.0M
24KK0004Feb 8, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SALAGSAG, SALAY, MISAMIS ORIENTALCompleted₱5.9M
24KK0005Feb 8, 2024CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY YUNGOD, SALAY, MISAMIS ORIENTALCompleted₱3.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.