Project 17LD0153
DPWH infrastructure contract
Contract ID:
17LD0153
Fingerprint:
2c56d0336263b1…a78a74fbba Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 20, 2017 (8 yrs 10 mo ago) · Target/actual end Apr 18, 2018
Description:
CONSTRUCTION OF CLASSROOMS, 1STY 2CL DONGAN PEKONG ES, MATANAO, DAVAO DEL SUR
Category:
Buildings and Facilities
Implementing office:
DPWH Davao del Sur DEO · Region XI
Contractor:
DAVAO SANTHONY BUILDERS CORPORATION · DPWH contractor code 40275
Contract amount:
₱2,852,860.20 (₱2.9M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| cf5c927fd700… | Dec 12, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR 1ST | ₱2,786,337.52 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LD0193 | Feb 23, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)-K1575+035-K1575+322, K1582+670-, K1582+714, K1592+100-K1592+1078, DAVAO DEL SUR | On-Going | ₱94.8M |
| 25LD0202 | Sep 22, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT.)-K1579+093-K1580+625, DAVAO DEL SUR | Completed | ₱95.9M |
| 25LD0203 | Sep 22, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SUR | Completed | ₱96.1M |
| 25LD0157 | Jun 25, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE-CONCRETE REVETMENT AT MATANAO RIVER ALONG MATANAO NHS LEFT SIDE DOWNSTREAM SECTION PHASE I, MATANAO, DAVAO DEL SUR | On-Going | ₱122.8M |
| 25LD0205 | Jun 3, 2025 | CONSTRUCTION OF EVACUATION CENTER, BARANGAY SAN VICENTE, MATANAO, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0018 | Mar 26, 2025 | PREVENTIVE MAINTENANCE OF ROAD; ASPHALT OVERLAY- DAVAO- COTABATO RD (JCT DIGOS-COTABATO SECT)-K1575+565-K1576+140, K1582+714-K1582+844, K1585+241-K1585+700, DAVAO DEL SUR | On-Going | ₱96.3M |
| 25LD0056 | Mar 26, 2025 | CONSTRUCTION OF ROAD, CENTRO KIBAO TO PUROK 3, BARANGAY KIBAO, MATANAO, DAVAO DEL SUR | On-Going | ₱19.8M |
| 25LD0206 | Mar 26, 2025 | CONCRETING OF BRGY. CAMANCHILES FMR, BRGY. CAMANCHILES, MATANAO, DAVAO DEL SUR | Completed | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.