Project 17M00060
DPWH infrastructure contract
Contract ID:
17M00060
Fingerprint:
e0caa99d902610…af7753865e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 6, 2018 (8 yrs 9 mo ago) · Target/actual end Nov 4, 2018
Description:
ROAD WIDENING OD DAVAO-COTABATO ROAD (KAYAGA-TUNGGOL SECTION), K1653+700-K1654+020; K1654+620-K1658+180, DATU MONTAWAL, MAGUINDANAO.
Category:
GAA 2017 LFP
Implementing office:
DPWH Region XII · Region XII
Contract amount:
₱106,187,395.56 (₱106.2M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MD0062 | Jul 30, 2025 | CONSTRUCTION OF MARIDAGAO RIS PROTECTION DIKE AT PULANGI RIVER, NABUNDAS, PIKIT, COTABATO | Terminated | ₱0 |
| 25M00007 | Jul 9, 2025 | CONSTRUCTION OF PULANGI RIVERBANK PROTECTION (DOWNSTREAM OF CARMEN BR., RIGHT BANK), PHASE III, STA. 0+652.5 - STA. 01+286.5, BARANGAY UGALINGAN, CARMEN, COTABATO | On-Going | ₱167.0M |
| 24M00328 | Jul 4, 2025 | ROAD CONCRETING IN SITIO BAYA TO SITIO DAGADANGEN, BARANGAY KILANGAN, PAGALUNGAN, MAGUINDANAO DEL SUR | On-Going | ₱39.3M |
| 24M00330 | Jul 4, 2025 | IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II AT BARANGAY DUNGGUAN, DATU MONTAWAL, MAGUINDANAO DEL SUR | On-Going | ₱14.3M |
| 25MI0034 | Feb 26, 2025 | CONSTRUCTION OF LUMAYONG FLOOD CONTROL PROJECT (DOWNSTREAM OF CARMEN BRIDGE, KAYAGA TO SITIO PUNOL, PHASE V) ALONG PULANGI RIVER, KABACAN COTABATO | Completed | ₱136.3M |
| 24MI0099 | Nov 27, 2024 | CONSTRUCTION OF WATER SYSTEM LEVEL II AT BRGY. KAYAGA, KABACAN, NORTH COTABATO | Completed | ₱9.9M |
| 24MI0060 | Mar 25, 2024 | BUKIDNON-COTABATO RD (KAYAGA COMMON JCT)-(S00808MN) CHAINAGE 000 - CHAINAGE 465 | Completed | ₱22.1M |
| 24M00061 | Mar 18, 2024 | CONSTRUCTION OF PULANGI RIVER FLOOD CONTROL PROJECT, DOWNSTREAM OF PAGALUNGAN BRIDGE, STA. 0+000-STA. 0+612, PIKIT, NORTH COTABATO | Completed | ₱117.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.