Project 17MD0200
DPWH infrastructure contract
Contract ID:
17MD0200
Fingerprint:
535bcc63a0a702…e444dde211 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 24, 2017 (8 yrs 10 mo ago) · Target/actual end Apr 11, 2018
Description:
CLUSTER F - CONST. OF UNIQUE WORKSHOP BUILDINGS 1 & 2, SILIK HS, PIKIT, COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
Contract amount:
₱6,122,106.63 (₱6.1M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MD0080 | Apr 7, 2026 | CONSTRUCTION OF 1STY 3CL SCHOOL BUIDING LANGAYEN ES, PIKIT, NORTH COTABATO | On-Going | ₱9.5M |
| 24MD0089 | Mar 7, 2025 | CONCRETING OF JUNCTION PROVINCIAL ROAD AT BARANGAY SILIK TO PAIDU PULANGI, PIKIT, NORTH COTABATO | Completed | ₱91.4M |
| 22MD0074 | Apr 5, 2022 | CONSTRUCTION OF BRIDGE - CONSTRUCTION OF BRIDGE IN SILIK, PIKIT, NORTH COTABATO | Completed | ₱29.2M |
| 22MD0015 | Feb 2, 2022 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY KOLAMBOG, PIKIT, NORTH COTABATO | Completed | ₱4.9M |
| 22MD0016 | Feb 2, 2022 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY PAIDU PULANGI, PIKIT, NORTH COTABATO | Completed | ₱4.9M |
| 22MD0017 | Feb 2, 2022 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY PUNOL, PIKIT, NORTH COTABATO | Completed | ₱4.9M |
| 21MD0023 | Apr 7, 2021 | CONCRETING OF G. GOKOTANO STREET, BARANGAY POBLACION, PIKIT, NORTH COTABATO | Completed | ₱2.0M |
| 20MD0005 | Nov 25, 2020 | PREVENTIVE MAINTENANCE OF ROADS: ASPHALT OVERLAY ALONG DUALING-BALIKI-SILIK ROAD (S00810MN), ALEOSAN AND PIKIT, NORTH COTABATO | Completed | ₱42.2M |