Project 17MG0119
DPWH infrastructure contract
Contract ID:
17MG0119
Fingerprint:
b608a216a714db…670861e319 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 3, 2017 (9 yrs ago) · Target/actual end Sep 28, 2018
Description:
CONSTRUCTION OF 1 UNIT-1STY 2CL AT DIENTE ES, LAKE SEBU, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
KGD BUILDERS INC. · DPWH contractor code 21960
Contract amount:
₱2,423,136.33 (₱2.4M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0017 | Jun 17, 2026 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE-SURALLAH-LAKE SEBU-MAITUM RD-K1745+300-K1745+453 | On-Going | ₱35.2M |
| 26MG0010 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1757+291-K1757+760 | On-Going | ₱9.1M |
| 26MG0012 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1759+000-K1761+020 | Completed | ₱21.9M |
| 26MG0011 | Jun 4, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+815-K1757+291 | Completed | ₱19.7M |
| 25MG0112 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, UBO ELEMENTARY SCHOOL-LAMFENEK EXTENSION, BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Completed | ₱5.0M |
| 25M00052 | Aug 5, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO | On-Going | ₱93.6M |
| 25MG0110 | Jun 27, 2025 | CLUSTER I-A.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), KIANTAY ELEMENTARY SCHOOL, SITIO KIANTAY, BRGY. UPPER SEPAKA, SURALLAH, SOUTH COTABATO B.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), NEW TUPI IS, SITIO NEW TUPI, BRGY. NED, LAKE SEBU, S | Completed | ₱2.6M |
| 25MG0016 | Apr 11, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+262-K1755+815, SOUTH COTABATO | Completed | ₱13.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.