Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17MG0173

DPWH infrastructure contract
Contract ID:
17MG0173
Fingerprint:
79804d3124d42a…13f182ce62 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 18, 2018 (8 yrs 9 mo ago) · Target/actual end Nov 20, 2018
Description:
CONSTRUCTION OF 1 UNIT-2STY 4CL AT SOTELO ES, NORALA, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
Contractor:
NASCON BUILDERS · DPWH contractor code 14786
Contract amount:
₱8,920,031.69 (₱8.9M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fde4fbf68906…Dec 22, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO DEO₱8,920,031.69

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.