Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17NG0046

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","17NG0046","CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (CLUSTERED) A. PILAR CENTRAL ELEMENTARY SCHOOL, PILAR, SURIGAO DEL NORTE B. SAN ISIDRO CENTRAL ELEMENTARY SCHOOL, SAN ISIDRO, SURIGAO DEL NORTE AND 15  OTHER LOCATIONS","Water Provision and Storage","Completed",3270703.44,0,100,"Surigao del Norte 1st DEO","Region XIII","TWO J.E. CONSTRUCTION AND SUPPLY (38726)","2017-11-19","2018-01-28",2017,"Regular Infra - GAA 2017 MFO-3",9.7211,125.973,"1606707000","1606700000"]
SHA-256
68b750abcdba133991023bb58e496531f958d45148424d676448bfc85e253c64

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.