Project 18BF0117
DPWH infrastructure contract
Contract ID:
18BF0117
Fingerprint:
1c1f07f3bf9deb…ad85fa8ebb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 4, 2018 (8 yrs 1 mo ago) · Target/actual end Jan 17, 2019
Description:
CONCRETING OF BRGY. SAN ANTONINO - BRGY. MASIGUN FMR, BRGY. SAN ANTONINO AND BRGY. MASIGUN, BURGOS, ISABELA
Category:
Roads
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
I.G.D. CONSTRUCTION AND DEVELOPMENT · DPWH contractor code 42947
Contract amount:
₱4,726,245.29 (₱4.7M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 67dc9bdf81a1… | Sep 17, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 2ND DEO | ₱4,726,245.29 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26BF0002 | Jun 15, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS TERTIARY ROAD - GAMU-ROXAS RD - K0405 + 744 - K0406 + 039, K0408 + 262 - K0408 + 411, BURGOS, ISAB | Completed | ₱7.5M |
| 25BF0108 | Oct 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY CULLALABO DEL SUR, BURGOS, ISABELA | Completed | ₱16.3M |
| 25BF0082 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, BURGOS, ISABELA | On-Going | ₱4.8M |
| 25BF0063 | Jun 16, 2025 | OO2:FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES DRAINAGE SYSTEMS -CONSTRUCTION OF BUGNAY CREEK FLOOD CONTROL PROJECT, DALIG SECTION, BURGOS, ISABELA | On-Going | ₱140.4M |
| 25BF0027 | Jun 9, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. SAN MIGUEL, BURGOS, ISABELA | On-Going | ₱4.9M |
| 25BF0026 | Mar 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CALIGUIAN, BURGOS, ISABELA | Completed | ₱4.9M |
| 25BF0030 | Mar 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY DIVISORIA, AURORA, ISABELA | Completed | ₱3.0M |
| 24BF0122 | Oct 14, 2024 | RAINWATER COLLECTOR SYSTEM, 1. SAN ROQUE ELEMENTARY SCHOOL, BURGOS, ISABELA, 2. SAN BONIFACIO ELEMENTARY SCHOOL, BURGOS, ISABELA, 3. SIMIMBAAN INTEGRATED SCHOOL, ROXAS, ISABELA, 4. DIVISORIA ELEMENTARY SCHOOL, AURORA, ISABELA, 5. MACUGAY ELEMENTARY SCHOO | Completed | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.