Project 18CC0330
DPWH infrastructure contract
Contract ID:
18CC0330
Fingerprint:
528c216cbdb9db…265af8ab26 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 8, 2018 (7 yrs 11 mo ago) · Target/actual end Jun 10, 2019
Description:
CONSTRUCTION OF TWO STOREY SIX CLASSROOM - IBA NATIONAL HIGH SCHOOL HAGONOY, BULACAN
Category:
Buildings and Facilities
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
ELDICO BUILDERS · DPWH contractor code 26601
Contract amount:
₱14,806,685.96 (₱14.8M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0dc006de328c… | Sep 18, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO | ₱14,806,685.96 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CC0352 | May 23, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN AGUSTIN, HAGONOY, BULACAN | On-Going | ₱9.6M |
| 25CC0480 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY SAN NICOLAS, HAGONOY, BULACAN | On-Going | ₱14.5M |
| 25CC0516 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, EUGENIO G. SY TAMCO ELEMENTARY SCHOOL, HAGONOY, BULACAN | On-Going | ₱14.5M |
| 25CC0538 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN SEBASTIAN, HAGONOY, BULACAN | On-Going | ₱18.4M |
| 25CC0312 | Mar 27, 2025 | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SAN AGUSTIN (PARONG PARONG), HAGONOY, BULACAN | On-Going | ₱69.3M |
| 25CC0451 | Mar 27, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CHECK GATE), BARANGAY TAMPOK, AND BARANGAY SANTA MONICA, HAGONOY, BULACAN | On-Going | ₱19.1M |
| 25CC0212 | Mar 21, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN NICOLAS, HAGONOY, BULACAN | On-Going | ₱14.3M |
| 25CC0227 | Mar 21, 2025 | REHABILITATION OF ROAD AT BARANGAY ABULALAS, HAGONOY, BULACAN | On-Going | ₱14.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.