Project 18CE0025
DPWH infrastructure contract
Contract ID:
18CE0025
Fingerprint:
1999246a5ea68c…54b38d90a7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 3, 2018 (8 yrs 7 mo ago) · Target/actual end Aug 30, 2018
Description:
ASSET PRESERVATION - CONSTRUCTION/UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS TERTIARY ROADS, JCT PINAGPANAAN - RIZAL - PANTABANGAN RD - K0150+729 - K0151+492
Category:
Roads
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
NERY'S CONSTRUCTION · DPWH contractor code 40606
Contract amount:
₱6,451,318.26 (₱6.5M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 904746d6aa58… | Mar 15, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - N. ECIJA 1ST DEO | ₱6,451,318.26 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26CE0025 | Jul 10, 2026 | ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, BONGABON-RIZAL-AURORA RD - K0153 + 452 - K0153 + 718 | On-Going | ₱4.7M |
| 25CE0160 | Jul 1, 2025 | CONSTRUCTION OF BOX CULVERT, BARANGAY VILLA LABRADOR, RIZAL, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0197 | Jul 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DEL PILAR, RIZAL, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0270 | Jun 11, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, BONGABON - RIZAL - AURORA RD - K0148 + (-335) - K0149 + 579, K0151 + 000 - K0152 + 000 | Completed | ₱95.5M |
| 25CE0108 | May 22, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BARANGAY POBLACION NORTE, MUNICIPALITY OF RIZAL, NUEVA ECIJA | Completed | ₱144.7M |
| 25CE0260 | Mar 31, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZENS CENTER), RIZAL, NUEVA ECIJA | Completed | ₱9.9M |
| 25CE0279 | Mar 31, 2025 | CONCRETING OF BRGY. CANAAN WEST FMR, BRGY. CANAAN WEST, RIZAL, NUEVA ECIJA | Completed | ₱14.8M |
| 25CE0280 | Mar 31, 2025 | CONCRETING OF BRGY. PACO ROMAN FMR, BRGY. PACO ROMAN, RIZAL, NUEVA ECIJA | Completed | ₱14.8M |