Hashed input (canonical JSON of the source row)
["dpwh","18FD0101","CONSTRUCTION OF CLASSROOMS (BATCH 3), SAN FERNANDO NHS, SAN FERNANDO, CAMARINES SUR","Buildings and Facilities","Completed",23559257.69,0,100,"Camarines Sur 2nd DEO","Region V","E.S. BIHAG CONSTRUCTION & SUPPLY (35698)","2018-12-04","2019-05-02",2018,"Outside Infra - GAA 2018 DepEd BEFF",13.56458,123.1453,"501732000","501700000"]
SHA-256
1ba54cd27628cb58a0152f8afa26f22d5d19377658de6893badd893385e3c140

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.