FY2026 GAA: ₱6.79T
PisoScan

Project 18FL0095

DPWH infrastructure contract
Contract ID:
18FL0095
Fingerprint:
c140c3d6db83c4…c3b0f227c5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 18, 2018 (7 yrs 10 mo ago) · Target/actual end Sep 15, 2019
Description:
NEW CONSTRUCTION OF BHS AND NEW CONSTRUCTION OF RHU, BULAN, SORSOGON
Category:
Buildings and Facilities
Implementing office:
Contractor:
LIENEL BUILDERS AND SUPPLY · DPWH contractor code 40023
Contract amount:
₱12,965,483.72 (₱13.0M)
Funding source:
Outside Infra - GAA 2018 DOH HFEP
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fba8f2d34961…Nov 28, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SORSOGON 2ND DEO₱12,965,483.72

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26FL0001Aug 14, 2026REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - BANUANG DAAN BR. (B00191LZ) ALONG GATE - BULAN AIRPORT RD, BULAN, SORSOGONOn-Going₱5.7M
26FL0043Aug 14, 2026CONSTRUCTION (COMPLETION) OF PUBLIC WATER SUPPLY SYSTEM, BARANGAY RECTO, BULAN, SORSOGONOn-Going₱2.9M
26FL0006Aug 3, 2026ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - GATE - BULAN AIRPORT RD - K0632 + 879 - K0633 + 000, BULAN, SORSOGONOn-Going₱1.4M
25FL0097Aug 27, 2025CONST. OF DRAINAGE SYSTEM, BARANGAY ZONE 6 (POBLACION), BULAN, SORSOGONOn-Going₱4.9M
25FL0066Jul 28, 2025CONST OF MP BUILDING (COVERED COURT) AT BRGY. SAGRADA, BRGY. SANTA REMEDIOS, BRGY. RECTO, BRGY. SOMAOn-Going₱88.2M
25FL0067Jul 25, 2025CONST. OF MP BUILDING (COVERED COURT) AT BRGY. NASUJE, BRGY. GATE, BRGY. SAN RAMON, BRGY. SAN VICENTOn-Going₱43.7M
25FL0069Jul 25, 2025CONST OF MP BUILDING (COVERED COURT) AT BRGY. N. ROQUE, BRGY. OSMENA, BRGY. OTAVI, BRGY. QUEZON ANDOn-Going₱34.0M
25FL0077Jul 25, 2025CONST. OF MP BUILDING (COVERED COURT) AT BRGY. SULANGAN, MATNOG, BRGY. CALPI, BULAN AND BRGY. DOLOS,On-Going₱29.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.