Project 18G00051

DPWH infrastructure contract
Contract ID:
18G00051
Fingerprint:
7ff3953dfae01f…15dc5a7c93 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 8, 2018 (8 yrs 6 mo ago) · Target/actual end Feb 29, 2020
Description:
PONTEVEDRA BR. (B00395NR) ALONG BACOLOD SOUTH RD. INCL. ROW
Category:
Bridges
Implementing office:
DPWH Region VI · Region VI
Contract amount:
₱97,355,144.95 (₱97.4M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26RB0064Jul 16, 2026INSTALLATION OF SOLAR STREET LIGHTS ALONG BACOLOD SOUTH ROAD - K0046 + (-908) - K0050 + 500, HINIGARAN, NEGROS OCCIDENTALOn-Going₱47.4M
25RD0095Jul 16, 2025CONSTRUCTION OF ROADS (SITIO LIBOT LIBOT BRGY. PANDAN UP TO BRGY. PROPER), PONTEVEDRA, NEGROS OCCIDENTALOn-Going₱9.8M
25GN0061Jun 16, 2025ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - JCT SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0043+000 - K0044+989, K00045+497 - K0045+821, K0046+079 - K0046+365On-Going₱45.1M
25GN0066Jun 16, 2025CONSTRUCTION OF BARANGAY HALL FOR BARANGAY RECREO, PONTEVEDRA, NEGROS OCCIDENTALCompleted₱4.9M
25GN0067Jun 16, 2025CONSTRUCTION OF BARANGAY HALL FOR BARANGAY MABINI, PONTEVEDRA, NEGROS OCCIDENTALCompleted₱4.9M
25GN0018Apr 10, 2025CONSTRUCTION OF TUBOG RELOCATION, BARANGAY CANROMA, TO MUNICIPAL GOVERNMENT CENTER ROAD, BARANGAY CANROMA, PONTEVEDRA, NEGROS OCCIDENTALCompleted₱4.9M
25GN0022Apr 10, 2025CONSTRUCTION OF SITIO SAMPAGUITA, BARANGAY ANTIPOLO TO MUNICIPAL GOVERNMENT CENTER ROAD, BARANGAY ANTIPOLO, PONTEVEDRA, NEGROS OCCIDENTALCompleted₱4.9M
25GN0034Apr 10, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAN JUAN RIVER, PONTEVEDRA, NEGROS OCCIDENTALOn-Going₱94.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.