Project 18GB0186
DPWH infrastructure contract
Contract ID:
18GB0186
Fingerprint:
eefefbdbc22834…32266e0f27 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 13, 2018 (7 yrs 11 mo ago) · Target/actual end Jan 17, 2020
Description:
CONSTRUCTION OF 2 STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING AT BITADTON ES, CULASI, ANTIQUE
Category:
Buildings and Facilities
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
FLT ENTERPRISES · DPWH contractor code 23039
Contract amount:
₱17,086,914.02 (₱17.1M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 65c303c06857… | Nov 23, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ANTIQUE DEO | ₱17,086,914.02 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GB0144 | Feb 2, 2026 | CONSTRUCTION OF CLASSROOMS, LIPATA-LAMPUTONG INTEGRATED SCHOOL, CULASI, ANTIQUE | On-Going | ₱9.4M |
| 25GB0045 | Mar 27, 2025 | CONSTRUCTION OF CONCRETE ROAD-BRGY. CAMANCIJAN- BRGY. ALOJIPAN ROAD LEADING TO MT. MADIA-AS CULASI, ANTIQUE | Completed | ₱9.8M |
| 25G00010 | Mar 6, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - PANGANTA BR. (B00356PN) ALONG ILOILO-ANTIQUE RD | Completed | ₱46.1M |
| 25GB0034 | Mar 4, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE -BITADTON BR. (B00358PN) ALONG ILOILO-ANTIQUE RD CULASI, ANTIQUE | On-Going | ₱19.6M |
| 25GB0040 | Mar 4, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE- SAN ANTONIO BR. (B00350PN) ALONG ILOILO-ANTIQUE RD CULASI,ANTIQUE | On-Going | ₱14.7M |
| 25GB0016 | Feb 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PANINGAYAN NHA HOUSING, CULASI, ANTIQUE | Completed | ₱4.9M |
| 24GB0146 | Nov 11, 2024 | EXPANSION OF SEAWALL ALONG BARANGAY CENTRO NORTE - LIPATA, CULASI, ANTIQUE | Completed | ₱41.8M |
| 24GB0117 | May 8, 2024 | CONSTRUCTION OF 1-STOREY 4-CLASSROOM SCHOOL BUILDING IN FLORES INTEGRATED SCHOOL BARANGAY FLORES, CU | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.