Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18GP0074

DPWH infrastructure contract
Contract ID:
18GP0074
Fingerprint:
929ff53e959bde…7aac52cad5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 14, 2018 (8 yrs 5 mo ago) · Target/actual end Feb 17, 2019
Description:
CONCRETING OF BRGY. STO. ROSARIO - BRGY. SAN JOSE FMR, BRGY. STO. ROSARIO, SAN JOSE, JAMINDAN, CAPIZ
Category:
Roads
Implementing office:
DPWH Capiz 2nd DEO · Region VI
Contractor:
CLY - ABC BUILDERS · DPWH contractor code 39231
Contract amount:
₱6,824,342.43 (₱6.8M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3c12bfa475be…May 30, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION VI₱6,824,342.43

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GP0021Apr 5, 2025CONSTRUCTION OF CONCRETE ROAD- ACCESS ROAD LEADING TO PANGABITKABITON FALLS, JAMINDAN, CAPIZOn-Going₱6.3M
25GP0036Mar 26, 2025RETROFITTING OF JAGNAYA BRIDGE, BARANGAY JAGNAYA, JAMINDAN, CAPIZOn-Going₱50.6M
25GP0031Mar 7, 2025CONSTRUCTION OF CONCRETE ROAD - SITIO LOMBOY, BRGY. LINAMBASAN TO BRGY. GANZON, BRGY. JAENA AND BRGY. SAN JUAN TO NATIONAL HIGHWAY IN SUPPORT OF ABACA INDUSTRY, JAMINDAN, CAPIZOn-Going₱14.7M
24GP0007Feb 19, 2024CONSTRUCTION OF CONCRETE ROAD- ACCESS ROAD LEADING TO PANGABITKABITON FALLS, JAMINDAN, CAPIZCompleted₱14.7M
24GP0015Feb 19, 2024CONSTRUCTION OF CONCRETE ROAD- SITIO LOMBOY, BRGY. LINAMBASAN TO BRGY. GANZON, BRGY. JAENA AND BRGY. SAN JUAN TO NATIONAL HIGHWAY IN SUPPORT OF ABACA INDUSTRY, JAMINDAN, CAPIZOn-Going₱24.2M
24GP0030Feb 19, 2024CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY PANGABAT, JAMINDAN, CAPIZCompleted₱9.9M
24GP0037Feb 19, 2024CONCRETING OF ROAD, BRGY. LAPAZ, JAMINDAN, CAPIZCompleted₱9.9M
24GP0038Feb 19, 2024CONCRETING OF ROAD, BRGY. CARIDAD, JAMINDAN, CAPIZCompleted₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.