Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18MA0059

DPWH infrastructure contract
Contract ID:
18MA0059
Fingerprint:
cbb7abd677f6d3…a8cd2eec7f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 25, 2018 (8 yrs ago) · Target/actual end Jan 12, 2019
Description:
ROAD CONSTRUCTION / CONCRETING OF NITUAN-BULDON ROAD, JUNCTION TO ORING ROAD, BULDON, MAGUINDANAO
Category:
Roads
Implementing office:
Contractor:
STONELINE CONSTRUCTION · DPWH contractor code 13132
As listed: STONELINE CONSTRUCTION (FORMERLY: ABUBAKAR ENGINEERING EXPONENT)
Contract amount:
₱19,204,660.04 (₱19.2M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
242a136fccb2…Oct 16, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII - COTAB₱18,204,660.04

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24M00253Jun 11, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, MATAYA, BULDON, MAGUINDANAO DEL NORTECompleted₱4.9M
23M00185Oct 5, 2023CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (TRAINING CENTER), BRGY. EDCOR, BULDON, MAGUINDANAOCompleted₱3.1M
23M00179Sep 28, 2023CONSTRUCTION OF SOLAR WATER SYSTEM, BULDON, MAGUINDANAO DEL NORTEOn-Going₱9.6M
23M00107Apr 12, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, KARIM, BULDON, MAGUINDANAOCompleted₱4.9M
23M00104Apr 5, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, DINGANEN, BULDON, MAGUINDANAOCompleted₱4.9M
21MA0001Sep 6, 2021CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY ARATUC, BULDON, MAGUINDANAOCompleted₱3.0M
20MA0140Mar 1, 2021CONSTRUCTION OF 1ST 2CL, CENTRAL ORING PS, BULDON, MAGUINDANAOCompleted₱5.0M
20MA0063Oct 22, 2020CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CALAAN, BULDON, MAGUINDANAOCompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.