Project 18MF0105
DPWH infrastructure contract
Contract ID:
18MF0105
Fingerprint:
1c141020e5ad81…ca9dc62276 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 15, 2018 (8 yrs 2 mo ago) · Target/actual end Aug 31, 2019
Description:
CONSTRUCTION OF 3-STY 3-CLASSROOMS LABORATORY BLDG. AT PIMBALAYAN NHS, LAMBAYONG (MARIANO MARCOS), SULTAN KUDARAT.
Category:
Buildings and Facilities
Implementing office:
DPWH Sultan Kudarat 1st DEO · Region XII
Contractor:
BLIMEX CONSTRUCTION & SUPPLY · DPWH contractor code 27259
Contract amount:
₱17,720,923.93 (₱17.7M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2df5d604491a… | Jul 31, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT DEO | ₱17,720,923.93 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25M00260 | Aug 13, 2025 | PREVENTIVE MAINTENANCE - DULAWAN-MARBEL RD - K1752 + 600 - K1753 + 600, LAMBAYONG, SULTAN KUDARAT | Completed | ₱70.1M |
| 25MF0038 | Jul 28, 2025 | 3CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS), CONST. OF RWCS AT BARANGAY HALL, BARANGAY LAGAO, LAMBAYONG, SULTAN KUDARAT, CONST. OF RWCS AT BARANGAY HALL, BARANGAY KATITISAN, LAMBAYONG, SULTAN KUDARAT, CONST. OF RWCS AT BARANGAY HEALTH CENTER, BA | Completed | ₱2.6M |
| 25MF0009 | Feb 17, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, ALA RIVER, TAGA SECTION - UPSTREAM (L/S),LAMBAYONG, SULTAN KUDARAT | Completed | ₱144.6M |
| 25MF0019 | Feb 17, 2025 | CONSTRUCTION OF CONCRETE ROAD - JUNCTION PROVINCIAL ROAD TO NEW CEBU - PIMBALAYAN - MAMALI ROAD IN SUPPORT TO AGRI-BUSINESS INDUSTRIES, BANANA PLANTATION/PROCESSING PLANT, LAMBAYONG, SULTAN KUDARAT | On-Going | ₱34.1M |
| 25MF0033 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY ZENEBEN, LAMBAYONG, SULTAN KUDARAT | Completed | ₱3.0M |
| 25MF0034 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL BUILDING),BARANGAY UDTONG, LAMBAYONG, SULTAN KUDARAT | Completed | ₱3.9M |
| 24MF0043 | Apr 12, 2024 | CONSTRUCTION OF MULTI PURPOSE BUILDING SANGGUNIANG KABATAAN HALL, BARANGAY POBLACION, LAMBAYONG, SULTAN KUDARAT | Completed | ₱7.9M |
| 24MF0003 | Feb 15, 2024 | DULAWAN-MARBEL RD - K1742 + (-599) - K1742 + (-335), K1742 + (-260) - K1744 + 380, PINGUIAMAN, LAMBAYONG, SULTAN KUDARAT | Completed | ₱124.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.