Project 18OA0124
DPWH infrastructure contract
Contract ID:
18OA0124
Fingerprint:
767ce3bc74e637…84f40208d1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 22, 2019 (7 yrs 9 mo ago) · Target/actual end Jan 18, 2020
Description:
CONSTRUCTION OF FOUR (4) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING, IMELDA ELEM. SCHOOL, MAL. CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Malabon-Navotas DEO · National Capital Region
Contractor:
TRIUMPH BUILDERS & STEEL, INC. · DPWH contractor code 2272
Contract amount:
₱29,694,849.81 (₱29.7M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| dd5d3d8fa9a0… | Dec 20, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MALABON-NAVOTAS SD | ₱29,694,849.81 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OA0101 | May 14, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, LONGOS ES, CITY OF MALABON | Completed | ₱2.3M |
| 25OD0361 | Jul 28, 2025 | CONSTRUCTION (COMPELTION) OF TESDAMAN MULTI-PURPOSE BUILDING, BRGY. 80, CALOOCAN CITY (PHASE 3) | On-Going | ₱80.4M |
| 25OD0182 | Jun 23, 2025 | STREETLIGHTING ALONG TAMARAW HILLS ROAD BRGY. MARULAS, VALENZUELA CITY | Completed | ₱5.8M |
| 25OD0183 | Jun 23, 2025 | STREETLIGHTING ALONG T. SERRANO ST. TO TAMARAW HILL BRGY. MARULAS, VALENZUELA CITY | On-Going | ₱6.7M |
| 25OD0186 | Jun 23, 2025 | ROADSAFETY: STREETLIGHTING ALONG PIO - T. CONCEPCION - INDEPENDENCE, BARANGAY GEN T. DE LEON VALENZUELA CITY | Completed | ₱21.1M |
| 25OD0190 | Jun 23, 2025 | ROADSAFETY: STREETLIGHTING ALONG JP. RIZAL TO GEN LUNA, BARANGAY KARUHATAN VALENZUELA CITY | On-Going | ₱9.3M |
| 25OD0238 | Jun 23, 2025 | STREETLIGHTING ALONG SAMAPGUITA ST., BARANGAY MARULAS, VALENZUELA CITY | On-Going | ₱6.3M |
| 25OD0240 | Jun 23, 2025 | STREETLIGHTING ALONG FAUSTO ST., BRGY.MARULAS, VALENZUELA CITY | On-Going | ₱5.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.